Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 5 phases, about 20 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Scope | Choose framework and scope | 5 days | Day 1 | Nothing (starts first) |
| Scope | Select auditor | 10 days | Day 6 | Choose framework and scope |
| Assess | Gap assessment | 10 days | Day 16 | Select auditor |
| Assess | Risk assessment | 5 days | Day 26 | Gap assessment |
| Remediate | Write or update policies | 14 days | Day 31 | Risk assessment |
| Remediate | Implement missing controls | 30 days | Day 45 | Write or update policies |
| Remediate | Employee security training | 7 days | Day 75 | Implement missing controls |
| Remediate | Vendor reviews | 10 days | Day 82 | Employee security training |
| Evidence | Evidence collection | 21 days | Day 92 | Vendor reviews |
| Evidence | Readiness review | 5 days | Day 113 | Evidence collection |
| Evidence | Fix readiness findings | 10 days | Day 118 | Readiness review |
| Audit | Audit fieldwork | 10 days | Day 128 | Fix readiness findings |
| Audit | Respond to auditor requests | 5 days | Day 138 | Audit fieldwork |
| Audit | Report received | 1 day | Day 143 | Respond to auditor requests |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this compliance audit preparation plan
Whether it is a SOC 2 report, an ISO certification or an internal audit, preparation follows the same shape: decide the scope, find the gaps, close them, collect evidence and run a readiness check before the auditor arrives. This plan gives each step its own row and owner.
It is a planning aid, not compliance advice. Your auditor and framework define what is actually required.
Who it's for: Security, compliance and operations leads at small and mid-size companies.
How to use it
- Open the plan. Click Use this template.
- Assign control owners. Give every remediation task an owner from engineering, HR or operations.
- Run remediation tracks in parallel. Unlink policies, controls, training and vendor reviews so they run together. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Share with leadership. Share a read-only link for status updates.
Planning tips
- Collect evidence as controls go live rather than at the end.
- Have someone who didn't build the controls run the readiness review.
- Book the auditor early; their calendars fill up.
Frequently asked questions
- How long does audit preparation take?
- It depends on how many gaps you find. This template spans about five months in sequence; parallel remediation shortens it.
- Does this template make us compliant?
- No. It organizes the work; your framework and auditor determine the requirements.
- Can I export the plan for the board?
- Print to PDF from your browser is on Solo ($12/month).
Related templates and guides
- ERP Implementation Plan Gantt chart template
- Data Migration Plan Gantt chart template
- Clinical Trial Timeline Gantt chart template
- ISO 27001 Certification Plan Gantt chart template
- SOC 2 Readiness Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.