Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 5 phases, about 39 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Prepare | Business case and vendor selection | 30 days | Day 1 | Nothing (starts first) |
| Prepare | Project kickoff and governance | 3 days | Day 31 | Business case and vendor selection |
| Prepare | Requirements and process design | 30 days | Day 34 | Project kickoff and governance |
| Build | System configuration | 45 days | Day 64 | Requirements and process design |
| Build | Integrations | 30 days | Day 109 | System configuration |
| Build | Reports and dashboards | 14 days | Day 139 | Integrations |
| Data | Data cleansing | 30 days | Day 153 | Reports and dashboards |
| Data | Migration trial run | 7 days | Day 183 | Data cleansing |
| Data | Second migration trial | 7 days | Day 190 | Migration trial run |
| Test | System integration testing | 14 days | Day 197 | Second migration trial |
| Test | User acceptance testing | 14 days | Day 211 | System integration testing |
| Deploy | End-user training | 14 days | Day 225 | User acceptance testing |
| Deploy | Cutover and go-live | 3 days | Day 239 | End-user training |
| Deploy | Hypercare support | 30 days | Day 242 | Cutover and go-live |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this erp implementation plan
ERP projects often run late not because of configuration but because data isn't clean or users aren't trained. This plan gives data migration its own trial runs and puts training right before go-live.
It fits a single-wave rollout for a small or mid-size company working with an implementation partner.
Who it's for: IT leads, finance leaders and implementation consultants.
How to use it
- Open the plan. Click Use this template.
- Run data cleansing in parallel. Unlink data cleansing so it starts during configuration. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Add your modules. Split configuration into finance, inventory, sales or whichever modules you are deploying.
- Share with the steering group. Use a read-only link for status meetings.
Planning tips
- Run at least two migration trials before cutover.
- Schedule training close to go-live so people remember it.
- Plan hypercare through the first month-end close on the new system.
Frequently asked questions
- What are the phases of an ERP implementation?
- Selection and planning, requirements and design, configuration and integrations, data migration, testing, training, go-live and post-go-live support.
- Can I break this into multiple waves?
- Yes. Duplicate rows per module or wave and link them so later waves start after earlier ones stabilize.
- How long can the plan be?
- Up to two years in the editor.
Related templates and guides
- Cutover Plan Gantt chart template
- RFP Timeline Gantt chart template
- Data Migration Plan Gantt chart template
- Compliance Audit Preparation Plan Gantt chart template
- Office Move Plan Gantt chart template
- Sprint planning on a Gantt chart
- Microsoft Project alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.