Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 4 phases, about 10 weeks if every task runs in sequence.
What's in the template
Source inventory and owners
Data mapping and transformation rules
Data quality assessment
Data cleansing
Migration scripts
Rollback plan
First test load
Validation and reconciliation
Second test load
Sign-off from data owners
Freeze changes in source
Production migration
Post-migration validation
Decommission old system
| Phase | Task | Example duration |
|---|---|---|
| Assess | Source inventory and owners | 5 days |
| Assess | Data mapping and transformation rules | 10 days |
| Assess | Data quality assessment | 5 days |
| Build | Data cleansing | 10 days |
| Build | Migration scripts | 10 days |
| Build | Rollback plan | 2 days |
| Rehearse | First test load | 2 days |
| Rehearse | Validation and reconciliation | 5 days |
| Rehearse | Second test load | 2 days |
| Rehearse | Sign-off from data owners | 2 days |
| Cutover | Freeze changes in source | 1 day |
| Cutover | Production migration | 2 days |
| Cutover | Post-migration validation | 2 days |
| Cutover | Decommission old system | 14 days |
Durations are examples to replace with your own estimates, not benchmarks.
About this data migration plan
Migrations go smoothly when they are rehearsed. This plan includes two test loads with validation between them, a written rollback plan, and decommissioning of the old system once the new one is trusted.
It suits moving a database, CRM or file store to a new platform.
Who it's for: Data engineers, IT managers and systems administrators.
How to use it
- Open the plan. Click Open in the editor.
- Add your systems. Rename rows to your source and target systems and assign data owners.
- Mark the freeze and cutover. Turn them into milestones so stakeholders see the window.
- Share with owners. Send a read-only link to every data owner.
Planning tips
- Reconcile row counts and totals after every test load.
- Write the rollback plan before the first production load, not during it.
- Keep the old system read-only for a while before decommissioning it.
Frequently asked questions
- What are the steps in a data migration?
- Inventory, mapping, quality assessment, cleansing, scripting, test loads with validation, sign-off, freeze, production load, validation and decommissioning.
- How many test loads should I run?
- At least one full rehearsal. This template plans two so fixes from the first can be verified.
- Is there an ERP template?
- Yes, see the ERP implementation template.