Create a data lake implementation Gantt chart. Track ingestion pipeline design, storage setup, catalog, governance, and analytics layer milestones. Free online tool.
A data lake without governance is a data swamp. Raw data piles up, nobody can find anything, quality is unknown, and analysts spend more time cleaning data than analyzing it. The promise of "store everything, figure out the schema later" only works if you build the governance, cataloging, and quality infrastructure alongside the ingestion pipelines.
A data lake implementation Gantt chart ensures that governance isn't an afterthought. The catalog is built as the first pipelines land. Data quality rules are defined before data accumulates. Access controls are designed before sensitive data flows in. gantt-chart.io is free and requires no account.
Data Lake ImplementationFirst Data Available for Analytics as the early milestoneData lake zone architecture defined — Week 1Technology stack selected — Week 1-2Data source prioritization — Week 2Access control and security model — Week 2-3Governance framework selected — Week 3Architecture approved — Week 3 (milestone)Storage buckets/containers provisioned — Week 3-4IAM roles and access policies — Week 4-5Encryption configured (at rest and in transit) — Week 4-5Network isolation and VPC endpoints — Week 5Data catalog service configured (AWS Glue, Azure Purview) — Week 5-6Cost management and lifecycle policies — Week 6Infrastructure ready — Week 6 (milestone)Build pipelines in priority order, starting with highest-value data sources:
Priority 1 Sources (Week 6-10):
Source 1: [Primary database] CDC pipeline — Week 6-8Source 2: [SaaS tool] API ingestion — Week 7-9Source 3: [Event stream] Kafka/Kinesis ingestion — Week 8-10Data landing in raw zone validated — Week 10Priority 2 Sources (Week 10-14):
Source 4-6: additional systems — Week 10-14Priority 3 Sources (Week 14-16):
Remaining sources — Week 14-16For each pipeline:
Catalog schema defined — Week 7Automated metadata capture from pipelines — Week 8-10Business glossary defined — Week 10-12Data lineage tracking configured — Week 11-13Search and discovery UI tested — Week 13-14Catalog operational — Week 14 (milestone)PII data classification scan — Week 8-10Data quality rules defined per dataset — Week 9-12Data quality checks automated in pipelines — Week 11-14Data retention policies implemented — Week 12-14Sensitive data access controls applied — Week 13-15Data quality dashboard — Week 15-16Governance operational — Week 16 (milestone)Query engine configured (Athena, Synapse, BigQuery) — Week 12-13dbt project set up — Week 13Core dbt models (key business entities) — Week 13-16BI tool connected (Tableau, Looker, Power BI) — Week 15-17First analytics dashboard from data lake — Week 17 (milestone)Self-serve analytics documentation — Week 18The bronze/silver/gold (or raw/curated/analytics) pattern prevents data corruption:
| Zone | What's here | Who writes | Who reads |
|------|-------------|-----------|-----------|
| Raw | Exact source copy, immutable | Ingestion pipelines only | Ingestion pipelines |
| Curated | Cleaned, conformed, typed | Transformation jobs | Analytics engineers |
| Analytics | Aggregated, query-optimized | dbt models | BI tools, analysts |
Never overwrite raw zone data. If a pipeline bug corrupts curated data, you can always reprocess from raw.
No catalog from the start. Adding metadata retrospectively to a lake with hundreds of tables is a months-long project. Build catalog alongside the first pipelines.
Storing everything without retention policies. Storage is cheap but not free. Data that's never queried after 6 months should be tiered to cold storage. Build retention policies before the lake fills up.
Build your data lake implementation timeline at gantt-chart.io—free, no account required.