A Gantt chart is a schedule drawn as bars on a timeline. Each row is a task, the bar's position shows when it happens and its length shows how long it takes. Arrows between bars show which task has to finish before another can start, and diamonds mark milestones such as an approval or a launch.
The steps below work in any tool: paper, a spreadsheet or a Gantt chart app. The order matters more than the tool. Most bad Gantt charts skip step 4 and draw bars at guessed dates, which is why they stop matching reality the first time something slips.
The 7 steps
- Write down the finish line. Name the deliverable and the event that ends the project: a launch, a handover, a submission. It decides what belongs on the chart. Work that doesn't lead to that finish line goes on a different plan.
- Break the work into tasks. List the work as tasks that one person or team can finish, then group them into phases such as Plan, Build and Launch. Split any task long enough that you couldn't tell halfway through whether it is on track.
- Estimate a duration for each task. Give each task a length in working days. Ask the person who will do the work, and write down the assumption behind any estimate you're unsure of, so it can be checked later.
- Link the dependencies. For every task ask: what has to finish before this can start? Draw that link. Most links are finish-to-start. Where there is a wait between two tasks, such as a review turnaround or concrete curing, add it as lag on the link rather than stretching the task.
- Set the start date and let the dates follow. Put the first task on your real start date. Every other task now starts when the tasks it depends on finish, which gives you a finish date you can defend instead of one you picked.
- Add milestones. Add zero-length milestones for the moments people ask about: sign-offs, go/no-go decisions, launch day. They make the chart readable at a glance for people who don't care about every task.
- Find the critical path, assign owners and share. The critical path is the longest chain of linked tasks. Any delay on it moves the finish date; tasks off it have slack. Give every task one owner, share the chart, and update it at a regular check-in rather than redrawing it when someone asks.
Worked example: a small website launch
Eight tasks with their durations and dependencies. Start and end days are worked out from the links, the same way a Gantt tool does it: each task starts the day after the latest of its predecessors ends.
| Task | Days | Waits for | Starts | Ends | Slack |
|---|---|---|---|---|---|
| A. Agree goals and sitemap | 3 | — | Day 1 | Day 3 | 0 (critical) |
| B. Write page copy | 8 | A | Day 4 | Day 11 | 7 days |
| C. Design page templates | 6 | A | Day 4 | Day 9 | 0 (critical) |
| D. Design review and sign-off | 2 | C | Day 10 | Day 11 | 0 (critical) |
| E. Build pages in the CMS | 7 | D | Day 12 | Day 18 | 0 (critical) |
| F. Add copy and images | 3 | B, E | Day 19 | Day 21 | 0 (critical) |
| G. Test on phones and browsers | 3 | F | Day 22 | Day 24 | 0 (critical) |
| H. Launch (milestone) | 0 | G | Day 24 | Day 24 | 0 (critical) |
The project finishes on day 24. Critical path: A → C → D → E → F → G → H.
Copy (B) can slip by seven days without moving launch day because it has slack: the design, review and build chain takes longer. A one-day delay to design review (D) moves launch by one day, because D is on the critical path. That is the question a Gantt chart answers that a task list can't.
Opens with the same links and parallel paths as above, and no account.
Common mistakes
- Drawing bars at dates instead of linking tasks. The chart looks right on day one and is wrong after the first delay.
- Tasks with no owner. A bar that belongs to everyone is the one nobody updates.
- Padding every task. Add one visible buffer before the deadline instead, so you can see how much of it has been used.
- Too much detail. If the chart has more rows than anyone will read, group the small tasks under one phase bar.
- Never updating it. A Gantt chart is a forecast; mark progress and move dates at each check-in.
Excel, Google Sheets or a Gantt chart tool?
A spreadsheet is fine for a short plan with few links. Once you need tasks to move together, a Gantt tool saves the formulas.
| Spreadsheet (Excel or Google Sheets) | Gantt chart tool | |
|---|---|---|
| Bars | Drawn with a stacked bar chart or conditional formatting | Drawn from start dates and durations |
| Dependencies | Only if you write a formula per task | Linked tasks move when one slips |
| Critical path | Worked out by hand | Calculated from the links |
| Sharing | Share the file | Share a link to the live chart |
| Cost | Usually already paid for | Free plans and paid plans vary by product |
Making one in gantt-chart.io
Paste a task list with durations, one task per line ("Design page templates 6d"), into the box on the homepage. You get a live Gantt chart with the tasks linked in order, without an account. Change the links, add milestones and the editor recalculates the dates and the critical path.
The Free plan saves 1 project and shares read-only links. Solo ($12/month) adds unlimited projects, CSV and JSON downloads and print to PDF.
Frequently asked questions
- What are the parts of a Gantt chart?
- A list of tasks down the side, a timeline across the top, a bar for each task showing its start and length, arrows for dependencies between tasks, and diamonds for milestones. Many charts also show progress inside each bar and a line for today.
- What is the critical path on a Gantt chart?
- It is the longest chain of dependent tasks from start to finish. A delay to any task on it delays the whole project; tasks off the critical path have slack and can slip by that much without moving the finish date.
- How detailed should a Gantt chart be?
- Detailed enough that every task has one owner and you can tell whether it is on track, and no more. Group small tasks under a phase bar when a chart has more rows than the people reading it will look at.
- Can I make a Gantt chart for free?
- Yes. You can build one in a spreadsheet, or paste a task list into gantt-chart.io without an account. The Free plan saves 1 project; downloads need Solo ($12/month).
- What is the difference between a Gantt chart and a timeline?
- A timeline shows when things happen. A Gantt chart also shows how long each task takes and which tasks depend on which, so it can show the effect of a delay. There is a longer comparison in our Gantt chart vs timeline guide.
Related
- Gantt chart examples
- Free Excel Gantt chart template
- Gantt chart in Google Sheets
- Gantt chart vs timeline
- Critical path method
- Free critical path calculator
- Project plan template
- Task dependency types explained
- PERT chart vs Gantt chart
- Website Redesign Plan template
- Construction Schedule template
- Marketing Launch Plan template
- Free Gantt chart maker, no sign-up
- All Gantt chart guides
Try it on your own plan
Paste a task list on the homepage and get a live Gantt chart with dependencies and a critical path. No account needed to try.