Plan infrastructure and utilities installation with a Gantt chart. Coordinate water, sewer, electrical, gas, and telecom installation across a development site.
On any new development site—residential subdivision, commercial park, or mixed-use district—the underground infrastructure must be installed before anything above grade can be built. Water mains, sanitary sewer, storm drainage, dry utilities (gas, electric, telecom), and road base are the foundation on which every building, street, and landscape element sits. They're also the part of a project that most frequently causes schedule delays.
Infrastructure installation is complex because it involves multiple independent utility providers (the water district, the gas company, the electric utility, and multiple telecom providers), each with their own permitting, design review, and inspection processes. You cannot install the electric conduit until the electric utility approves the design. You cannot install the gas main until the gas company approves and inspects. You cannot pour the street pavement until all underground utilities are installed and inspected. A single utility provider who takes 6 months to approve a design can hold up the entire site.
gantt-chart.io lets civil engineers and land developers build an infrastructure installation timeline that shows every utility's critical path—so you know in Month 1 which utility agreement will determine your construction start date.
Before building your infrastructure installation timeline:
Infrastructure Acceptance / Final Inspection as the red milestone. Add Grading Permit Issued, Water Service Agreement, and Electric Service Agreement as orange milestones.Grading permit application — submit after final engineering; 2-6 weeks reviewNPDES / stormwater permit — 2-6 months; submit concurrent with grading permitWater service agreement application — 3-9 months; utility board approval often requiredSewer service agreement application — 3-9 months; concurrent with waterElectric service agreement (PG&E, Xcel, local utility) — 3-12 months; design, capacity, and cost allocationGas service agreement — 2-6 monthsTelecom conduit design approvals (AT&T, Comcast, fiber) — 2-6 months eachRight-of-way permits (county / city) — 2-6 weeks; for any work in public ROWAll permits and agreements in hand — milestoneClearing and grubbing — 2-6 weeks; remove vegetation, trees, structuresRough grading / mass earthwork — 4-16 weeks; cut and fill to design gradesSubgrade preparation for streets — 2-4 weeksDetention / retention basin excavation — 2-6 weeksRough grading complete and inspected — milestoneWater main installation — 4-12 weeks depending on pipe length and sizeWater main pressure test and disinfection — 1-2 weeks; health department inspectionSanitary sewer main installation — 4-12 weeksSanitary sewer TV inspection — 1-2 weeks; camera inspection of every pipe segmentStorm drainage / detention outlet structures — 4-10 weeksStorm sewer installation — 4-10 weeks; can run concurrent with sanitaryWet utilities inspections and acceptance — milestoneGas main installation — 2-6 weeks; gas company inspects and acceptsElectric conduit installation (developer-installed) — 2-6 weeksElectric utility installation (utility-installed) — 4-12 weeks; utility sets its own schedule; coordinate closelyElectric transformer pads and vaults — 1-2 weeksTelecom conduit installation — 2-6 weeks; multiple providers may install simultaneouslyFiber optic conduit — 1-3 weeks; if separate from standard telecomStreet lighting conduit and foundations — 1-3 weeksDry utilities inspections and acceptance — milestoneAggregate base compaction (road base) — 2-4 weeks; must pass compaction testsCurb and gutter installation — 2-6 weeksSidewalk installation — 2-4 weeks; can run concurrent with curbStreet light fixture installation — 1-2 weeks; after conduit and pole baseAsphalt paving — base course — 1-3 weeksUtility service connections to individual lots — 2-6 weeks; water meters, sewer lateralsAsphalt paving — finish course — 1-2 weeks; often deferred until builder construction traffic is completeSignage and striping — 1 weekFinal infrastructure inspection and acceptance — milestone| Milestone | Typical Timing |
|-----------|----------------|
| Grading permit issued | Month 3-8 |
| Water service agreement executed | Month 6-15 |
| Electric service agreement executed | Month 6-18 |
| Grading complete | Month 8-20 |
| Water main accepted | Month 12-24 |
| Sewer main accepted | Month 12-24 |
| Dry utilities complete | Month 14-28 |
| Paving complete | Month 18-32 |
| Infrastructure acceptance | Month 20-36 |
gantt-chart.io includes an infrastructure and utilities installation timeline template with permitting, grading, wet utilities, dry utilities, and paving tracks pre-loaded. Open it, adjust for your specific site acreage and utility jurisdiction review times, and share with your civil engineer and utility contractor.