Plan your interior design project with a Gantt chart. Track concept, procurement, construction, and installation phases. Free browser tool, no sign-up required.
The most common failure mode in interior design projects isn't creative disagreement—it's lead time. Custom furniture takes 12–16 weeks. Tile from an overseas supplier takes 8–10 weeks. Wallcovering requires a sample approval before ordering. If the designer didn't account for these lead times in the project schedule, the client's move-in date arrives before the furnishings do.
Procurement is the long pole. Design decisions that aren't made by the order cutoff date cascade into delayed delivery, which delays installation, which delays occupancy. A Gantt chart that shows the order date → lead time → delivery window → installation window makes these dependencies obvious before they become problems.
An interior design project Gantt chart maps design phases, procurement windows, construction milestones, and installation scheduling in one view. gantt-chart.io lets designers and project managers build this quickly, free, no sign-up required.
Before building your interior design project timeline:
| Task | Duration | Depends On |
|------|----------|------------|
| Client discovery and needs assessment | 1–2 weeks | Project kickoff |
| Space measurement and documentation | 1 week | Site access |
| Concept development (mood boards, direction) | 1–2 weeks | Programming |
| Concept presentation and client approval | 1 week | Concept complete |
Get written approval on the design direction before moving to design development. Undocumented verbal approvals create scope disputes later.
| Task | Duration | Depends On |
|------|----------|------------|
| Floor plan and furniture layout | 1–2 weeks | Concept approved |
| Material and finish selections | 2–3 weeks | Layout approved |
| Custom piece specifications | 1–2 weeks | Layout and materials |
| Lighting design and electrical coordination | 1–2 weeks | Layout |
| Design development presentation | 1 week | All selections |
| Client approval of all selections | 1–2 weeks | Presentation |
Material and finish selections are the critical path gate for procurement. Any item requiring a client decision needs that decision before its order cutoff date—make this explicit in your schedule.
| Task | Duration | Depends On |
|------|----------|------------|
| Construction drawing package | 2–3 weeks | Design development approved |
| Contractor bid and selection | 2–3 weeks | CD package complete |
| Permit application (if required) | 2–8 weeks | CDs complete |
| Contractor contract execution | 1 week | Contractor selected |
If renovation work requires permits, start the permit process immediately after CDs are complete. Don't wait for contractor selection.
| Task | Lead Time | Order Cutoff |
|------|-----------|--------------|
| Custom upholstery and seating | 10–16 weeks | Early in design development |
| Custom case goods (cabinets, tables) | 10–14 weeks | Design development |
| Custom window treatments | 8–12 weeks | After measurements final |
| Lighting fixtures (custom or specialty) | 6–10 weeks | Design development |
| Tile and stone (especially imported) | 6–10 weeks | Design development |
| Wallcovering (after sample approval) | 4–8 weeks | Sample approved |
| Decorative accessories and art | 2–4 weeks | Near installation |
| Stock furniture (in-stock items) | 2–6 weeks | Later in project |
Model each procurement item as a bar from order date to delivery date. Overlay with the installation date to confirm delivery happens before installation.
| Task | Duration | Depends On |
|------|----------|------------|
| Demolition | 1–2 weeks | Permits, contractor mobilized |
| Structural work (if any) | 2–4 weeks | Demolition |
| MEP rough-in (electrical, plumbing, HVAC) | 2–4 weeks | Structural |
| Drywall, taping, and priming | 1–2 weeks | MEP rough-in |
| Painting | 1–2 weeks | Drywall |
| Flooring installation | 1–2 weeks | Paint complete |
| Built-in millwork installation | 1–2 weeks | Flooring |
| Trim and finish work | 1 week | Millwork |
| Final MEP trim-out and inspection | 1 week | Finishes |
| Task | Duration | Depends On |
|------|----------|------------|
| Furniture delivery and placement | 1–3 days | Construction complete, items delivered |
| Window treatment installation | 1–2 days | Furniture placed |
| Lighting installation and programming | 1 day | Electrical complete |
| Art and accessory placement | 1–2 days | Furniture set |
| Punch list walkthrough | 1 day | Installation complete |
| Photography | 1 day | Styling complete |
| Client handover | 1 day | Punch list resolved |
Open gantt-chart.io, enter your procurement items with lead times, overlay construction phases, and share with your client and contractors. Free, no account required.