Plan a land development and entitlement project with a Gantt chart. Track due diligence, rezoning, infrastructure approvals, and lot delivery milestones.
Raw land development—turning a parcel into finished lots or a ready-to-build site—is one of the longest-cycle activities in real estate. A typical suburban residential land development project (rezoning raw land, subdividing into lots, installing infrastructure, and delivering finished lots to homebuilders) takes 3-7 years from land acquisition to first home under construction. The waiting happens in regulatory queues: rezoning hearings, subdivision plat approvals, environmental clearances, utility service agreements, and infrastructure permit reviews. The working happens in compressed bursts of engineering, grading, and utility installation.
Developers who don't track the entitlement process with a project plan tend to have carrying costs that erode returns. Every month of unplanned delay on a $10M land acquisition carries $50,000-$100,000 in interest cost. When those delays accumulate across a 4-year entitlement process, the cost of poor scheduling can eliminate a project's entire profit margin.
A land development entitlement project plan in gantt-chart.io makes the regulatory critical path explicit, shows which approvals gate subsequent approvals, and gives your equity partners a realistic picture of when lots will be delivered.
Before building your land development entitlement project plan:
First Lot Delivery to Builder as the hard red milestone. Add Rezoning Approved, Final Plat Recorded, and Infrastructure Complete as orange milestones.Land acquisition — milestoneALTA survey — 3-5 weeksPhase I Environmental — 3-4 weeksWetlands delineation — 4-8 weeks; must be done during growing seasonGeotechnical investigation — 3-6 weeks; test boring locations across siteHydrology and drainage study — 4-8 weeksPreliminary site plan / lot layout — 4-8 weeks; based on survey and constraintsTraffic impact analysis — 8-14 weeksUtility availability study — 4-8 weeks; confirm capacity at nearest connection pointsDue diligence and preliminary engineering complete — milestonePre-application meeting with planning — 2-4 weeks to scheduleRezoning / PUD application preparation — 4-8 weeksRezoning application submittal — milestonePlanning department review period — 60-180 days per jurisdictionCommunity meetings / neighborhood outreach — 2-6 months concurrent with reviewPlanning commission hearing — milestone; 2-6 months after submittalCity/county council approval — milestone; 1-4 months after planning commissionRezoning effective — milestone; often 30 days after council votePreliminary plat application — can begin concurrent with rezoning in some jurisdictionsPreliminary plat review — 60-120 daysPreliminary plat approved — milestoneFinal engineering (grading, drainage, utilities) — 3-6 monthsFinal plat application — after final engineeringFinal plat review and approval — 30-90 daysPlat recorded — milestone; legal lots created upon recordingHOA documentation filed — concurrent with final platWater and sewer service agreement — 3-9 months; utility board approval often requiredStormwater / NPDES permit — 2-6 monthsRoad/access permit (state DOT if arterial access) — 2-6 monthsArmy Corps 404 permit (if wetlands impacted) — 3-18 monthsGrading permit — 2-6 weeks after plat approvalUnderground utility installation permits — 2-4 weeksAll permits in hand — milestoneClearing and grubbing — 2-6 weeksMass grading — 4-12 weeksDetention / retention pond construction — 4-8 weeksUnderground utilities (water, sewer, storm) — 4-12 weeksDry utilities (gas, electric, telecom) — 4-8 weeksStreet base and paving — 4-8 weeksInfrastructure inspections and acceptance — 2-6 weeksFinal grading and erosion control — 2-4 weeksFirst lot delivery to builder — milestone| Milestone | Typical Timing |
|-----------|----------------|
| Land acquisition | Month 0 |
| Due diligence complete | Month 3-6 |
| Rezoning application submitted | Month 6-10 |
| Rezoning approved | Month 12-24 |
| Preliminary plat approved | Month 15-30 |
| Final plat recorded | Month 24-42 |
| Infrastructure permits in hand | Month 30-48 |
| Infrastructure construction complete | Month 36-60 |
| First lot delivery | Month 38-66 |
| Final lot delivery | Month 42-72 |
gantt-chart.io includes a land development and entitlement project plan template with regulatory, engineering, and infrastructure tracks pre-loaded. Open it, adjust for your jurisdiction's review timelines, and share with your civil engineer, entitlement attorney, and equity partners.