An office tenant improvement project is constrained from both ends. On the front end, you can't start construction until the lease is signed and the landlord approves construction drawings—which takes weeks. On the back end, the business has a current lease expiration (or a workforce that can't be in limbo indefinitely). The window between lease execution and required occupancy is typically 12-24 weeks, and every week consumed by slow permitting, late design decisions, or uncoordinated trades is a week the business absorbs the cost of holding two spaces or negotiating expensive holdover rent.
Office fit-outs are also technically complex. A 10,000 SF open-plan office with conference rooms, a server room, kitchen, and reception requires electrical at every workstation, data cabling to every desk, HVAC balancing for occupancy loads, AV systems in every conference room, and security access control at every door. Coordinating these systems without a project schedule means AV contractors show up to install screens when electricians are still roughing in power. IT cabling gets installed before conduit is in place. Move-in is scheduled before punch list is complete.
gantt-chart.io lets corporate real estate teams and project managers build a TI timeline that keeps design, permitting, construction, and technology installation coordinated against a fixed move-in date.
Before building your office fit-out timeline:
Move-In / Occupancy as the hard red milestone. Add Permit Issued, Substantial Completion, and Technology Cutover as orange milestones.Space programming — 1-2 weeks; block plans, headcount allocation, room countsSchematic design — 2-4 weeks; initial floor plan optionsDesign development — 2-4 weeks; selected plan with furniture layoutConstruction documents — 3-5 weeks; permit-ready drawingsFurniture plan finalized — milestone; needed before FF&E procurement beginsAV / IT design — 2-4 weeks; runs concurrent with CD phaseLandlord drawing approval — 1-3 weeks after CD submittalBuilding permit submittal — milestonePermit issued — milestoneFurniture specification — 2-3 weeks; finalize vendor and productFurniture order placed — milestone; custom / semi-custom takes 10-16 weeksFurniture delivery to site — milestone; plan delivery for Week 2 after substantial completionFurniture installation — 1-2 weeksTask lighting and accessories installation — 2-3 daysDemolition (if previously built-out space) — 1-2 weeksRough framing (walls, doors, glass partitions) — 1-3 weeksPlumbing rough-in (kitchen, restrooms if modifying) — 1-2 weeksElectrical rough-in — 2-4 weeks; includes outlets, circuits, dedicated server room powerData / low-voltage rough-in — 2-3 weeks; conduit, J-hooks, boxesHVAC modifications — 2-4 weeks; ductwork, VAV boxes, thermostatsRough-in inspections — milestoneDrywall — 1-3 weeksPaint — 1-2 weeksCeiling tile and grid — 1-2 weeksFlooring (carpet, LVT, polished concrete) — 1-2 weeksMillwork (kitchen, reception desk, built-ins) — 1-3 weeksLighting fixture installation — 1 weekSubstantial completion — milestoneData cabling pull — 1-2 weeks; after conduit rough-inNetwork equipment installation (IDF, switches) — 1 weekAV equipment installation (displays, conferencing) — 1-2 weeks; after ceiling and walls completeSecurity / access control installation — 1 weekIT system testing and cutover — 1 weekAV system testing and commissioning — 1 weekTechnology punch list — 3-5 daysMove plan developed — 4 weeks before move; floor-by-floor, department-by-departmentMove vendor engaged — 8-12 weeks before moveEmployee communications about move — begin 8 weeks before moveIT equipment decommission at old space — 1-2 weeks before movePhysical move — after hours / weekend — 1-3 weekendsIT equipment recommission at new space — 1-2 days after moveOld space surrender and condition review — within 30 days of move| Milestone | Typical Timing |
|-----------|----------------|
| Lease executed | Week 0 |
| Programming complete | Week 2-4 |
| Construction documents complete | Week 8-12 |
| Permit submitted | Week 10-14 |
| Furniture ordered | Week 8-12 |
| Permit issued | Week 14-20 |
| Construction start | Week 15-21 |
| Rough-in inspections passed | Week 20-28 |
| Substantial completion | Week 26-36 |
| Furniture installed | Week 28-38 |
| Technology cutover | Week 28-38 |
| Move-in / occupancy | Week 30-42 |