Office Fit-Out and Tenant Improvement Project Timeline

Plan an office fit-out and tenant improvement project with a Gantt chart. Track design, permitting, construction, AV/IT installation, and move-in on one visual timeline.

Office Fit-Out and Tenant Improvement Project Timeline

The Problem: Office TI Projects Are Squeezed Between Lease Signing and Business Disruption

An office tenant improvement project is constrained from both ends. On the front end, you can't start construction until the lease is signed and the landlord approves construction drawings—which takes weeks. On the back end, the business has a current lease expiration (or a workforce that can't be in limbo indefinitely). The window between lease execution and required occupancy is typically 12-24 weeks, and every week consumed by slow permitting, late design decisions, or uncoordinated trades is a week the business absorbs the cost of holding two spaces or negotiating expensive holdover rent.

Office fit-outs are also technically complex. A 10,000 SF open-plan office with conference rooms, a server room, kitchen, and reception requires electrical at every workstation, data cabling to every desk, HVAC balancing for occupancy loads, AV systems in every conference room, and security access control at every door. Coordinating these systems without a project schedule means AV contractors show up to install screens when electricians are still roughing in power. IT cabling gets installed before conduit is in place. Move-in is scheduled before punch list is complete.

gantt-chart.io lets corporate real estate teams and project managers build a TI timeline that keeps design, permitting, construction, and technology installation coordinated against a fixed move-in date.


Prerequisites

Before building your office fit-out timeline:


Step-by-Step Instructions

Step 1: Set Up the TI Project Timeline

  1. Open gantt-chart.io
  2. Title it "[Company Name] — [Address] — [SF] SF — Move-In [Date]"
  3. For a typical office TI, set the view to cover 16-36 weeks from lease signing to move-in
  4. Use Week view—TI projects move fast and week-level precision matters
  5. Add Move-In / Occupancy as the hard red milestone. Add Permit Issued, Substantial Completion, and Technology Cutover as orange milestones.

Step 2: Programming and Design

  1. Create a task group: Programming & Design
  2. Add:

Step 3: FF&E Procurement

  1. Create a task group: Furniture, Fixtures & Equipment
  2. Add:

Step 4: Construction

  1. Create a task group: Construction
  2. Add:

Step 5: Technology Installation

  1. Create a task group: Technology & AV
  2. Add:

Step 6: Move Coordination

  1. Create a task group: Move Management
  2. Add:

Key Milestones

| Milestone | Typical Timing |

|-----------|----------------|

| Lease executed | Week 0 |

| Programming complete | Week 2-4 |

| Construction documents complete | Week 8-12 |

| Permit submitted | Week 10-14 |

| Furniture ordered | Week 8-12 |

| Permit issued | Week 14-20 |

| Construction start | Week 15-21 |

| Rough-in inspections passed | Week 20-28 |

| Substantial completion | Week 26-36 |

| Furniture installed | Week 28-38 |

| Technology cutover | Week 28-38 |

| Move-in / occupancy | Week 30-42 |


Common Mistakes


Template

gantt-chart.io includes an office fit-out and tenant improvement template with design, construction, technology, and move management tracks pre-loaded. Open it, enter your lease dates and target move-in, and share with your project manager, GC, and technology team.