How to Manage an Oil and Gas Pipeline Project Timeline

Plan an oil and gas pipeline project with a Gantt chart template covering FERC certification, right-of-way acquisition, environmental review, construction, and hydrostatic testing.

How to Manage an Oil and Gas Pipeline Project Timeline


The Problem: Pipeline Projects Fail on Permitting and Right-of-Way, Not Construction

Interstate natural gas pipeline projects are among the most regulated infrastructure undertakings in the United States. FERC Certificate of Public Convenience and Necessity proceedings under the Natural Gas Act involve a formal docketed proceeding with environmental review, public scoping, intervenor comment periods, and commissioner deliberation that routinely spans 18–36 months before construction authorization is granted.

Meanwhile, right-of-way (ROW) acquisition across hundreds or thousands of landowners — including condemnation proceedings for holdouts — runs on a parallel track with its own unpredictable timeline. Projects that assume FERC approval and ROW acquisition will complete on a developer-preferred schedule almost always encounter delays that cascade into construction season conflicts, steel pipe cost escalation, and contractor demobilization.

A pipeline project Gantt chart in gantt-chart.io maps the FERC proceeding, environmental mitigation, ROW acquisition, material procurement, and construction execution on a unified timeline so project teams can see conflicts before they become multi-million-dollar surprises.


Prerequisites


Oil and Gas Pipeline Project Timeline

Phase 1: FERC Pre-Filing and Route Engineering (Weeks 1–24)

Phase 2: FERC Environmental Review and Right-of-Way Acquisition (Weeks 20–72)

Phase 3: Material Procurement and Contractor Selection (Weeks 48–72)

Phase 4: Pipeline Construction (Weeks 68–100)

Phase 5: Hydrostatic Testing and In-Service (Weeks 96–112)


Common Mistakes


Timeline Summary

| Phase | Duration | Key Milestone |

|-------|----------|---------------|

| FERC Pre-Filing | Weeks 1–24 | FERC application filed |

| FERC Review & ROW | Weeks 20–72 | Certificate Order received |

| Procurement | Weeks 48–72 | Pipe ordered, contracts awarded |

| Construction | Weeks 68–100 | Pipeline welded and buried |

| Testing & In-Service | Weeks 96–112 | PHMSA authorization, gas in |


Next Steps

Pipeline projects span years and require coordination across federal agencies, state regulators, hundreds of landowners, and multiple construction contractors. The projects that stay on schedule are those with a unified project timeline that everyone from FERC counsel to the pipeline inspector can reference. Build your oil and gas pipeline project Gantt chart on gantt-chart.io and keep your development team, legal team, and construction contractors aligned on the path from FERC filing to first gas.