Use this website redesign project timeline template to manage design, development, content migration, and launch. Build a visual Gantt chart free online.
Website redesigns routinely double in scope and timeline. The original estimate was "three months" but it's now month six and the site still isn't live. The culprit is almost always one of three things: content migration takes far longer than expected, stakeholder feedback rounds multiply, or the development environment setup eats the first three weeks.
A website redesign project timeline built as a Gantt chart prevents these common failures. It forces you to schedule the content audit before development starts, limits feedback rounds to scheduled windows, and shows everyone—leadership, marketing, developers, the agency—the actual path from kickoff to launch. gantt-chart.io is free, browser-based, and shareable with no account required.
[Company] Website Redesign - [Year]Launch milestone at the endKickoff meeting with all stakeholders — Day 1Current site analytics audit — Week 1Content inventory and audit — Week 1-2Competitor and inspiration review — Week 1Brand and messaging alignment — Week 2Sitemap v1 approved — Week 2 (milestone)Information architecture and wireframes — Week 2-3Wireframe review and approval — Week 3 (milestone)Visual design: homepage and core templates — Week 3-5Design review round 1 — Week 5Design revisions — Week 5-6Design review round 2 and final approval — Week 6 (milestone)Design handoff to development — Week 6Limit to two review rounds. More rounds are a scope change—add them as tasks with extended timeline implications.
SEO keyword research — Week 2-3Copy brief for all pages — Week 3Copy draft: homepage and hero pages — Week 3-5Copy draft: product/service pages — Week 4-6Copy draft: about, team, case studies — Week 5-7Copy reviews and approvals — Week 6-7Final copy delivered to dev — Week 8Content almost always runs long. Build in a one-week buffer between copy approval and development integration.
Dev environment and CMS setup — Week 6Global components: header, footer, navigation — Week 6-7Homepage build — Week 7-8Interior page templates — Week 8-9Content integration — Week 9-10Forms, CRM, and analytics integrations — Week 9-10Redirect mapping and SEO implementation — Week 10Staging site ready for QA — Week 11 (milestone)Cross-browser testing — Week 11Mobile responsiveness testing — Week 11Performance audit (Core Web Vitals) — Week 11Accessibility audit (WCAG 2.1) — Week 11All links and forms tested — Week 11Stakeholder UAT review — Week 12Bug fixes — Week 12Launch sign-off — Week 12 (milestone)DNS cutover planned — Day before launchLaunch: DNS cutover and go-live — Launch day (milestone)Redirect verification — Launch dayAnalytics verification (GA4, tracking) — Launch day24-hour monitoring — Day 1Post-launch bug fixes — Week 1 post-launchSearch Console submit — Day 1No content timeline. Developers sit idle waiting for approved copy. Content work should start in parallel with design, not after design is approved.
Unlimited stakeholder rounds. Every additional feedback round adds 1–2 weeks. Lock in two rounds per phase during kickoff and enforce it.
No redirect plan. Every URL that changes needs a 301 redirect. Missing redirects destroy SEO value built over years. Schedule this explicitly in Week 10.
| Phase | Timeline |
|-------|---------|
| Discovery | Week 1-2 |
| Design | Week 2-6 |
| Content (parallel) | Week 2-8 |
| Development | Week 6-11 |
| QA | Week 11-12 |
| Launch | Week 12 |