What it does
The add-in opens as a pane next to your plan. Sign in to your gantt-chart.io account, choose Send to gantt-chart.io, and every task in the open project is sent to one gantt-chart.io plan. Tasks are matched by their Project task GUID, so sending again updates that plan instead of making a copy. The pane shows the linked plan's address and an Open in gantt-chart.io button.
What is sent
- Task names, start and finish dates, and percent complete
- The outline: top-level summary tasks become lanes, and summary tasks show as phase bars
- Milestones
- Predecessors with their link type (FS, SS, FF, SF) and lag
- Resource names and task notes
Plans
The add-in follows your gantt-chart.io plan. On Free, one linked plan counts as your 1 saved project. Solo ($12 a month) saves unlimited projects, so you can link as many Project files as you like. See pricing.
Two-way sync
The owner invites people to a linked plan by email, each with a role and, for team members, the Project resource name that is theirs. Members sign in to gantt-chart.io and edit only what their role allows. When the owner next opens the plan in Project, the add-in pane lists the waiting changes and applies them to the open file.
Roles
- Owner. The person who sent the plan. Every field they change in gantt-chart.io can flow back into Project, and they invite, re-role and remove members.
- Scheduler. Can change Start, Finish, Duration, % Complete and Notes on ordinary tasks. Summary tasks stay as Project calculates them.
- Team member. Can change % Complete and Notes only, and only on tasks assigned to their Project resource name.
- Viewer. Read-only. Sees the whole plan and changes nothing.
When a value changed in both places
If a field was changed in Project after a member made their change, the value in Project is kept and the change is marked as a conflict. The owner sees it in the pane and can choose to apply the member's value instead. Each change shows as pending, applied, rejected or conflict in the plan's Microsoft Project sync panel.
Install
The add-in manifest is at https://gantt-chart.io/addin/msproject/manifest.xml. Download it (right-click, Save link as) and use one of the options below.
Option 1: one computer (shared-folder catalog)
- Make a folder, for example
C:\AddinCatalog, and putmanifest.xmlin it. - Right-click the folder, choose Properties, then Sharing, then Share. Copy the network path it shows, such as
\\YOUR-PC\AddinCatalog. - In Microsoft Project choose File, Options, Trust Center, Trust Center Settings, then Trusted Add-in Catalogs.
- Paste the network path into Catalog Url, choose Add catalog, tick Show in Menu, then OK. Restart Project.
- Open a plan, go to Project, then My Add-ins (or Insert, then My Add-ins), choose Shared Folder, pick Gantt Chart Sync for gantt-chart.io and choose Add.
Option 2: your whole organization (Microsoft 365 admin center)
- A Microsoft 365 admin opens the admin center and goes to Settings, then Integrated apps.
- Choose Upload custom apps, pick Office Add-in, and upload
manifest.xml(or give the manifest URL above). - Choose who gets it: everyone, specific users or groups. Accept the permissions and finish.
- It can take up to 24 hours to appear. Users then find it in Project under My Add-ins, Admin Managed.
Option 3: Microsoft AppSource
An AppSource listing is planned but not yet available. Use option 1 or 2 for now.
First run
- Open the pane and choose Sign in to gantt-chart.io. A window opens where you sign in with Google or an email link. New to gantt-chart.io? The same step creates your account, with no card needed. No Microsoft password is shared with gantt-chart.io.
- If you used an email link, it opens in your browser. Choose Allow and connect there, copy the connection code, and paste it into the pane.
- Choose Send to gantt-chart.io. When it finishes, choose Open in gantt-chart.io.
- To invite people, open the plan in gantt-chart.io, open More, then Data studio, then the Microsoft Project sync tab.
The connection is an API key named “Microsoft Project add-in” in your account. Revoke it there to disconnect the add-in.
Support
In the store and in Project, the add-in is called Gantt Chart Sync for gantt-chart.io. It is made and supported by Morton Technology Consulting, LLC, not by Microsoft. For help installing it, signing in, or a sync that did not do what you expected, use the contact page and include the Project version and what the pane showed.
- Privacy policy, including exactly what the add-in reads and sends
- Terms of service, which are also the add-in's license agreement
- To disconnect, choose Sign out in the pane, or revoke the “Microsoft Project add-in” API key in your account.
Limits
- Windows only: Project Standard or Professional 2016, 2019, 2021 or 2024, or Project Online Desktop Client. Project for the web and Project on Mac do not run task pane add-ins with these features.
- Write-back needs the add-in in Project on the Windows desktop. Changes wait in gantt-chart.io until the owner opens the plan in Project and pulls them in; nothing changes the .mpp file on its own.
- Only the fields a person's role allows are sent back. Other edits made in gantt-chart.io stay in gantt-chart.io.
- Office.js returns predecessors as text, so links to other projects (inter-project links) are skipped.
- Dates are sent as calendar days; Project's working-time calendars and resource rates are not sent.
Prefer a file? You can import the .mpp file itself, or a .mpx or Project XML file.