Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 5 phases, about 16 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Define | Needs analysis | 7 days | Day 1 | Nothing (starts first) |
| Define | Learning outcomes | 5 days | Day 8 | Needs analysis |
| Define | Scope and sequence | 5 days | Day 13 | Learning outcomes |
| Design | Unit and lesson design | 20 days | Day 18 | Scope and sequence |
| Design | Assessments and rubrics | 10 days | Day 38 | Unit and lesson design |
| Design | Learning materials | 20 days | Day 48 | Assessments and rubrics |
| Review | Peer and stakeholder review | 7 days | Day 68 | Learning materials |
| Review | Accessibility check | 3 days | Day 75 | Peer and stakeholder review |
| Pilot | Pilot with one group | 20 days | Day 78 | Accessibility check |
| Pilot | Pilot feedback and revision | 10 days | Day 98 | Pilot with one group |
| Launch | Teacher or trainer briefing | 2 days | Day 108 | Pilot feedback and revision |
| Launch | Full rollout | 1 day | Day 110 | Teacher or trainer briefing |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this curriculum development plan
Good curriculum work starts with outcomes and works backward: what learners should be able to do, how you will assess it, and only then the lessons and materials. This plan follows that order and includes a pilot so problems surface before full rollout.
It suits a school course, a university module or a corporate training program. Add one row per unit if you want unit-level dates.
Who it's for: Teachers, instructional designers, curriculum coordinators and training managers.
How to use it
- Open the plan. Click Use this template. The tasks load as a live Gantt chart without signing in.
- Add units. Split unit design into one row per unit if several people write them.
- Fit the calendar. Line the pilot up with a real term or training cohort.
- Share. Send a read-only link to department heads or stakeholders.
Planning tips
- Write assessments before materials so lessons teach what is assessed.
- Pilot with a small group first.
- Keep a change log of what the pilot changed.
Frequently asked questions
- What is backward design?
- Planning a course from the desired outcomes, then assessments, then learning activities.
- Can I use this for online courses?
- Yes. There is also an online course development template with recording and platform setup rows.
- Is it free?
- Yes. Opening and editing the template is free, and a free account saves one project. Downloading the chart as PDF or CSV needs Solo.
Related templates and guides
- Online Course Development Plan Gantt chart template
- Thesis and Dissertation Timeline Gantt chart template
- Research Project Plan Gantt chart template
- Gantt chart in Google Sheets
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.