Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 16 tasks across 4 phases, about 47 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Proposal | Topic and research questions | 14 days | Day 1 | Nothing (starts first) |
| Proposal | Proposal draft | 21 days | Day 15 | Topic and research questions |
| Proposal | Proposal approval | 7 days | Day 36 | Proposal draft |
| Proposal | Ethics or IRB application and review | 30 days | Day 43 | Proposal approval |
| Research | Literature review | 45 days | Day 73 | Ethics or IRB application and review |
| Research | Methods and instruments | 14 days | Day 118 | Literature review |
| Research | Data collection | 60 days | Day 132 | Methods and instruments |
| Research | Data analysis | 35 days | Day 192 | Data collection |
| Writing | Draft results and discussion | 30 days | Day 227 | Data analysis |
| Writing | Draft introduction and conclusion | 14 days | Day 257 | Draft results and discussion |
| Writing | Advisor review and revisions | 21 days | Day 271 | Draft introduction and conclusion |
| Writing | Formatting and references | 7 days | Day 292 | Advisor review and revisions |
| Defense | Submit to committee | 1 day | Day 299 | Formatting and references |
| Defense | Defense preparation | 14 days | Day 300 | Submit to committee |
| Defense | Defense | 1 day | Day 314 | Defense preparation |
| Defense | Final corrections and submission | 14 days | Day 315 | Defense |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this thesis and dissertation timeline
Many graduate programs ask for a Gantt chart in the thesis or dissertation proposal. This template covers the standard path: proposal, ethics review where needed, literature review, data collection, analysis, chapter writing, advisor feedback and the defense.
Ethics or IRB approval sits on its own row because data collection with human participants usually can't begin without it, and review times vary by institution. Check your program's deadlines and replace the placeholders.
Who it's for: Master's and doctoral students, and advisors who track several students.
How to use it
- Open the timeline. Click Use this template to load the plan.
- Work back from your submission deadline. Set the final submission to your program's deadline and pull every earlier task into place.
- Overlap the literature review. Most students keep reading while collecting data. Unlink the literature review so it runs alongside methods and collection. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Share with your advisor. Share a read-only link. On Solo, print the chart to PDF for your proposal.
Planning tips
- Submit the ethics application as early as your program allows.
- Leave real time for advisor feedback; it is often the longest wait in the writing phase.
- Schedule formatting separately; reference and template checks take longer than expected.
Frequently asked questions
- How do I make a Gantt chart for my thesis proposal?
- List each research phase, estimate durations, link the ones that depend on each other (such as ethics approval before data collection), and set the final date to your submission deadline. This template starts you from that structure.
- Can my advisor see my timeline?
- Yes. Share a read-only link; your advisor does not need an account.
- Is there a template for a shorter research project?
- Yes. The research project template covers a single study without the thesis writing phases.
Related templates and guides
- Research Project Plan Gantt chart template
- Grant Proposal Timeline Gantt chart template
- Book Publishing Timeline Gantt chart template
- Gantt chart in Google Sheets
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.