Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 4 phases, about 10 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Research | Funder research and fit | 5 days | Day 1 | Nothing (starts first) |
| Research | Read guidelines and eligibility | 2 days | Day 6 | Funder research and fit |
| Research | Letter of intent | 5 days | Day 8 | Read guidelines and eligibility |
| Write | Project narrative draft | 14 days | Day 13 | Letter of intent |
| Write | Budget and budget justification | 7 days | Day 27 | Project narrative draft |
| Write | Evaluation plan | 5 days | Day 34 | Budget and budget justification |
| Write | Letters of support requested | 14 days | Day 39 | Evaluation plan |
| Review | Internal review | 5 days | Day 53 | Letters of support requested |
| Review | Revisions | 5 days | Day 58 | Internal review |
| Review | Finance and leadership sign-off | 3 days | Day 63 | Revisions |
| Submit | Final formatting and attachments | 2 days | Day 66 | Finance and leadership sign-off |
| Submit | Submission | 1 day | Day 68 | Final formatting and attachments |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this grant proposal timeline
Grant deadlines don't move, but internal sign-offs and partner letters of support often arrive late. This plan puts those dependencies ahead of the submission date.
Many funders also ask for a project timeline inside the proposal itself; you can build that chart in the same editor.
Who it's for: Grant writers, nonprofit development staff and researchers.
How to use it
- Open the plan. Click Use this template.
- Set the deadline. Move the submission to the funder's deadline, with a day of margin.
- Request letters early. Unlink letters of support so they start alongside the narrative. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Share with collaborators. Send a read-only link to partners and reviewers.
Planning tips
- Submit a day early; portals can be slow near deadlines.
- Build the budget alongside the narrative so the two match.
- Ask partners for letters with a draft paragraph they can adapt.
Frequently asked questions
- How far ahead should I start a grant proposal?
- Several weeks for most proposals, longer for large government grants. This template spans about two months.
- Can I include a Gantt chart inside the grant?
- Yes. Build the project timeline in the editor; print to PDF from your browser is on Solo.
- Can collaborators see the plan?
- Yes. Share a read-only link; recipients do not need an account.
Related templates and guides
- Research Project Plan Gantt chart template
- Thesis and Dissertation Timeline Gantt chart template
- Clinical Trial Timeline Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.