Plan a new home construction project with a Gantt chart timeline. Track permits, foundation, framing, MEP, finishes, and final inspections in one visual schedule.
Building a new home involves 20+ trade contractors whose work must happen in a specific sequence. Framing can't start until foundation is cured. Electrical rough-in can't be inspected until framing is complete. Drywall can't go up until all rough-in inspections pass. Flooring can't be installed until drywall is painted. When one trade runs 2 weeks late, every subsequent trade is pushed back, and subcontractors who were booked months in advance may not be available when you finally need them.
Custom home builders and owner-builders who rely on verbal schedules and phone calls to coordinate trades consistently overshoot their projected completion dates. The average custom home takes 6-18 months to build depending on size and complexity. Without a written timeline showing dependencies, it's impossible to know which delay is critical and which has slack.
A residential construction project timeline built in gantt-chart.io shows every phase, who's responsible for each trade, and what can't start until something else finishes. Inspectors, lenders with construction draws, and the homeowner all need to see where the project stands.
Before building your residential construction timeline:
Certificate of Occupancy as the hard red milestone. Add Framing Inspection Passed and Final Draw as orange milestones.Demolition / clearing — 1-3 weeks if existing structure or heavy vegetationRough grading — 1-2 weeksTemporary utilities (power, water) — 1 weekSurvey and layout — 2-3 daysExcavation — 3-10 days depending on basement depthFootings poured and inspected — milestone; 3-5 days plus inspection waitFoundation walls / slab prep — 1-3 weeksFoundation poured — milestoneWaterproofing and drainage — 1 week (basement) or concurrent with backfillBackfill and rough grade — 3-5 daysFoundation cure period — minimum 7 days before framing startsLumber delivery — schedule 1 week before framing startFloor system — 1-2 weeks for first floorWall framing — first floor — 1-2 weeksWall framing — second floor (if applicable) — 1-2 weeksRoof framing / trusses — 1-2 weeksSheathing and housewrap — 1 weekWindows and exterior doors rough-in — 1 weekFraming inspection — milestone; schedule with building departmentPlumbing rough-in — 2-3 weeksElectrical rough-in — 2-3 weeksHVAC ductwork and equipment rough-in — 2-3 weeksLow-voltage rough-in (data, audio, security) — 1 week; runs concurrent with electricalInsulation — 1 week after rough-insRough-in inspections (plumbing, electrical, mechanical) — milestoneInsulation inspection — milestoneDrywall hang — 1-2 weeksDrywall tape and mud — first coat — 3-5 daysDrywall second and third coats — 1 weekDrywall texture (if applicable) — 3-5 daysExterior siding / brick / stucco — 2-6 weeks depending on materialRoofing — 1-2 weeks; often runs concurrent with drywallExterior trim and paint — 1-2 weeksInterior paint — prime and finish — 1-2 weeksTrim carpentry (baseboards, door casings, built-ins) — 1-2 weeksCabinets installation — 1 weekCountertops template and install — 1 week template + 1-2 weeks fabrication + 2 days installTile work (bathrooms, kitchen backsplash) — 2-3 weeksFlooring (hardwood, LVP, carpet) — 1-2 weeksPlumbing trim-out (fixtures, toilets, faucets) — 3-5 daysElectrical trim-out (devices, fixtures, panel) — 3-5 daysHVAC trim-out and startup — 2-3 daysFinal grading and landscaping — 1-2 weeksFinal inspections — milestoneCertificate of Occupancy — milestone| Milestone | Typical Timing |
|-----------|----------------|
| Building permit issued | Week 1-8 |
| Foundation poured | Week 4-12 |
| Framing complete | Week 10-20 |
| Rough-in inspections passed | Week 18-28 |
| Drywall complete | Week 22-32 |
| Cabinets and countertops installed | Week 28-38 |
| Flooring complete | Week 32-42 |
| Final inspections | Week 38-52 |
| Certificate of Occupancy | Week 40-56 |
gantt-chart.io includes a residential construction timeline template with all the task groups above pre-loaded. Open it, fill in your specific trade contractors and permit dates, and share with your lender and homeowner for weekly progress updates.