Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 21 tasks across 6 phases, about 22 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Preconstruction | Permit application and plan review | 20 days | Day 1 | Nothing (starts first) |
| Preconstruction | Subcontractor bids and award | 10 days | Day 21 | Permit application and plan review |
| Preconstruction | Site survey and layout | 3 days | Day 31 | Subcontractor bids and award |
| Sitework | Clearing and grading | 5 days | Day 34 | Site survey and layout |
| Sitework | Utilities trenching | 5 days | Day 39 | Clearing and grading |
| Sitework | Footings excavation | 3 days | Day 44 | Utilities trenching |
| Structure | Footings and foundation pour | 7 days | Day 47 | Footings excavation |
| Structure | Foundation cure and inspection | 7 days | Day 54 | Footings and foundation pour |
| Structure | Framing | 20 days | Day 61 | Foundation cure and inspection |
| Structure | Roof sheathing and dry-in | 7 days | Day 81 | Framing |
| MEP | Plumbing rough-in | 6 days | Day 88 | Roof sheathing and dry-in |
| MEP | Electrical rough-in | 6 days | Day 94 | Plumbing rough-in |
| MEP | HVAC rough-in | 6 days | Day 100 | Electrical rough-in |
| MEP | Rough-in inspections | 3 days | Day 106 | HVAC rough-in |
| Finishes | Insulation and inspection | 4 days | Day 109 | Rough-in inspections |
| Finishes | Drywall hang and finish | 12 days | Day 113 | Insulation and inspection |
| Finishes | Interior trim and paint | 12 days | Day 125 | Drywall hang and finish |
| Finishes | Flooring and fixtures | 10 days | Day 137 | Interior trim and paint |
| Closeout | Final inspections | 3 days | Day 147 | Flooring and fixtures |
| Closeout | Punch list | 5 days | Day 150 | Final inspections |
| Closeout | Certificate of occupancy | 2 days | Day 155 | Punch list |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this construction schedule
A construction schedule lives or dies on sequence. Framing can't start until the foundation has cured and passed inspection; drywall can't go up until the rough-in inspections sign off on electrical, plumbing and HVAC. This template lays those gates out in order so the critical path is visible from the first day.
It is written for a small commercial or residential new build run by a general contractor. Durations are placeholders sized for a modest single-structure job; replace them with your subcontractors' quoted durations and your jurisdiction's inspection lead times.
Who it's for: General contractors, owner-builders and project engineers who need a schedule they can share with subs and the owner.
How to use it
- Open the template. Click Use this template. The schedule loads as a live Gantt with each activity chained finish-to-start, so you can see the full duration immediately.
- Replace durations with quotes. Click each bar and enter your subcontractors' quoted durations and your local inspection lead times. Downstream tasks move automatically.
- Overlap the trades that can overlap. Plumbing, electrical and HVAC rough-in often run in parallel. Remove the chain between them so they share the same window, and keep the inspection gate after all three. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Mark the inspections as milestones. Turn the inspection rows into milestones so the owner and lender see the gates at a glance, then share a read-only link.
Planning tips
- Add weather float to sitework and dry-in, the phases most exposed to rain delays.
- Order long-lead items (windows, trusses, switchgear) as separate tasks that start during preconstruction.
- Keep the inspection gates as their own rows; they are the dates most likely to slip and the easiest to forget.
Frequently asked questions
- What should a construction schedule include?
- At minimum: permits, sitework, foundation, structure, mechanical/electrical/plumbing rough-in, required inspections, finishes and closeout. Each phase should show its dependency on the inspection or trade before it.
- Can I share this schedule with subcontractors?
- Yes. Share links are read-only and recipients do not need an account. CSV downloads and print to PDF from your browser are on the Solo plan ($12/month).
- Is this a critical path schedule?
- The template opens with every task linked finish-to-start, so the whole chain is critical until you overlap trades. Once you run work in parallel, the editor shows which tasks still drive the finish date.
Related templates and guides
- 3-Week Look-Ahead Schedule Gantt chart template
- Home Renovation Plan Gantt chart template
- Kitchen Remodel Timeline Gantt chart template
- Office Move Plan Gantt chart template
- Construction scheduling with a Gantt chart
- Microsoft Project alternative for schedules
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.