Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 3 phases, about 6 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Prepare | Test scope and objectives | 3 days | Day 1 | Nothing (starts first) |
| Prepare | Review RTO and RPO targets | 2 days | Day 4 | Test scope and objectives |
| Prepare | Update runbooks | 5 days | Day 6 | Review RTO and RPO targets |
| Prepare | Notify stakeholders | 2 days | Day 11 | Update runbooks |
| Prepare | Verify backups and replication | 3 days | Day 13 | Notify stakeholders |
| Test | Pre-test checks | 1 day | Day 16 | Verify backups and replication |
| Test | Failover to recovery site | 1 day | Day 17 | Pre-test checks |
| Test | Validate applications and data | 1 day | Day 18 | Failover to recovery site |
| Test | Failback to primary | 1 day | Day 19 | Validate applications and data |
| Learn | Test report | 3 days | Day 20 | Failback to primary |
| Learn | Remediation actions | 15 days | Day 23 | Test report |
| Learn | Update DR plan | 3 days | Day 38 | Remediation actions |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this disaster recovery test plan
A disaster recovery (DR) test proves you can restore service within your recovery time objective (RTO) and lose no more data than your recovery point objective (RPO) allows. This plan covers preparation, the test itself, failing back, and fixing what the test exposed.
Keep the test day short and the preparation thorough. Durations are a working example for one application or system group.
Who it's for: IT operations managers, SRE teams and business continuity leads.
How to use it
- Open the plan. Click Use this template. The tasks load as a live Gantt chart without signing in.
- Fill in your targets. Rename the RTO and RPO row with your actual targets so the report can compare against them.
- Add systems. Add validation rows for each critical application.
- Share. Send a read-only link to stakeholders before the test window.
Planning tips
- Time each step on test day so the report shows actual recovery time.
- Include failback; it is often harder than failover.
- Track remediation actions to closure before the next test.
Frequently asked questions
- What are RTO and RPO?
- RTO is how quickly a service must be restored. RPO is how much data loss, measured in time, is acceptable.
- How often should DR be tested?
- Many organizations test at least yearly, and after major changes. Your policy or regulator may set a frequency.
- Is it free?
- Yes. Opening and editing the template is free, and a free account saves one project. Downloading the chart as PDF or CSV needs Solo.
Related templates and guides
- Cloud Migration Plan Gantt chart template
- IT Network Upgrade Gantt chart template
- ISO 27001 Certification Plan Gantt chart template
- Sprint planning on a Gantt chart
- Microsoft Project alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.