Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 11 tasks across 4 phases, about 19 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Example duration |
|---|---|---|
| Assess | Application and dependency inventory | 14 days |
| Assess | Migration approach per application | 7 days |
| Assess | Cost estimate and business case | 5 days |
| Foundation | Landing zone, networking and identity | 21 days |
| Foundation | Security baseline and monitoring | 10 days |
| Migrate | Pilot application migration | 10 days |
| Migrate | Wave one migration | 21 days |
| Migrate | Wave two migration | 21 days |
| Migrate | Final cutover window | 3 days |
| Optimize | Right-sizing and cost review | 14 days |
| Optimize | Decommission on-premises servers | 10 days |
Durations are examples to replace with your own estimates, not benchmarks.
About this cloud migration plan
Cloud migrations go in waves: a low-risk pilot proves the landing zone and runbook, then groups of applications move in planned windows. This plan keeps the pilot, waves and on-premises decommission as separate rows so progress is visible.
It fits moving a set of business applications from a data center or hosting provider to a public cloud.
Who it's for: IT directors, cloud architects and managed service providers.
How to use it
- Open the plan. Click Open in the editor.
- Group apps into waves. Rename the wave rows with the applications in each, or add a row per application.
- Keep windows visible. Keep the cutover window as a bar so its full length shows.
- Share the schedule. Send a read-only link to application owners.
Planning tips
- Map dependencies before choosing waves; tightly linked apps should move together.
- Use the pilot to test the rollback plan as well as the migration.
- Plan a cost review shortly after migration.
Frequently asked questions
- What is a landing zone?
- The prepared cloud environment — accounts, networking, identity and security controls — that migrated applications move into.
- Why migrate in waves?
- Waves limit risk and let the team improve the runbook between groups.
- Can the plan run past a year?
- Yes. Plans can run up to two years.