Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 5 phases, about 11 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Pre-boarding | Offer accepted and paperwork | 3 days | Day 1 | Nothing (starts first) |
| Pre-boarding | Equipment ordered and accounts created | 5 days | Day 4 | Offer accepted and paperwork |
| Pre-boarding | Buddy assigned and welcome note | 1 day | Day 9 | Equipment ordered and accounts created |
| First week | First day orientation and setup | 1 day | Day 10 | Buddy assigned and welcome note |
| First week | Team introductions | 2 days | Day 11 | First day orientation and setup |
| First week | Role training and documentation | 5 days | Day 13 | Team introductions |
| First month | First small project | 10 days | Day 18 | Role training and documentation |
| First month | Thirty-day check-in | 1 day | Day 28 | First small project |
| Second month | Own a core responsibility | 25 days | Day 29 | Thirty-day check-in |
| Second month | Sixty-day check-in | 1 day | Day 54 | Own a core responsibility |
| Third month | Independent project delivery | 25 days | Day 55 | Sixty-day check-in |
| Third month | Ninety-day review and goals | 1 day | Day 80 | Independent project delivery |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this employee onboarding plan
Good onboarding starts before day one: equipment ordered, accounts created, a buddy assigned. This template covers pre-boarding through the 90-day review so the hiring manager, IT and HR each see their part.
Open it for every new hire and rename the role-specific tasks.
Who it's for: Hiring managers, HR teams and people operations.
How to use it
- Open the plan. Click Use this template.
- Set the start date. Put the first day on the new hire's real start date and move pre-boarding before it.
- Assign owners. Set IT, HR, the manager and the buddy as owners on their tasks.
- Share with the new hire. Send a read-only link so they know what's coming.
Planning tips
- Order equipment at offer acceptance; shipping delays are common.
- Give the first project a clear finish line inside the first month.
- Put all three check-ins on the calendar on day one.
Frequently asked questions
- What is a 30-60-90 day onboarding plan?
- A plan that sets goals for a new hire's first, second and third months: learning the role, owning responsibilities, then delivering independently.
- Can I reuse this for every hire?
- Yes. Open the template for each new hire; Solo saves unlimited projects.
- Does the new hire need an account?
- No. Read-only share links work without signing in.
Related templates and guides
- Recruitment and Hiring Plan Gantt chart template
- Office Move Plan Gantt chart template
- ERP Implementation Plan Gantt chart template
- Performance Review Cycle Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.