Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 5 phases, about 16 weeks if every task runs in sequence.
What's in the template
Requirements and budget
Lease signed
Space plan and seating
Internet circuit order and install
Fit-out and furniture
Network and Wi-Fi setup
Movers booked
Staff communication and packing guide
Address change notices
Packing and labeling
Move weekend
IT setup and testing
Post-move support
Old office handover
| Phase | Task | Example duration |
|---|---|---|
| Plan | Requirements and budget | 5 days |
| Plan | Lease signed | 10 days |
| Plan | Space plan and seating | 10 days |
| Prepare | Internet circuit order and install | 30 days |
| Prepare | Fit-out and furniture | 25 days |
| Prepare | Network and Wi-Fi setup | 5 days |
| Prepare | Movers booked | 2 days |
| Communicate | Staff communication and packing guide | 3 days |
| Communicate | Address change notices | 5 days |
| Move | Packing and labeling | 3 days |
| Move | Move weekend | 2 days |
| Move | IT setup and testing | 2 days |
| Settle | Post-move support | 5 days |
| Settle | Old office handover | 5 days |
Durations are examples to replace with your own estimates, not benchmarks.
About this office move plan
Office moves are often paced by internet and network installation, which can take weeks to provision. This plan starts the circuit order early and keeps it visible.
It fits a small or mid-size office moving to one new location.
Who it's for: Office managers, operations leads and IT managers.
How to use it
- Open the plan. Click Open in the editor.
- Start the circuit order early. Unlink the internet install and start it as soon as the lease is signed. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Set the move date. Set the first task's start date, then adjust durations until move weekend lands on your planned date.
- Share with staff. Share a read-only link so everyone knows packing and move dates.
Planning tips
- Ask your provider for the circuit install lead time before you pick a move date.
- Label everything by seat number from the space plan.
- Keep the old office handover date in the plan; leases often specify it.
Frequently asked questions
- How long does an office move take to plan?
- Often a few months once the lease is signed, depending mostly on fit-out and network installation. This template spans three to four months.
- Can I share the plan with vendors?
- Yes, with a read-only link that needs no account.
- Can I export to PDF for leadership?
- PDF and CSV downloads are on Solo ($12/month).