Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 5 phases, about 16 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Plan | Requirements and budget | 5 days | Day 1 | Nothing (starts first) |
| Plan | Lease signed | 10 days | Day 6 | Requirements and budget |
| Plan | Space plan and seating | 10 days | Day 16 | Lease signed |
| Prepare | Internet circuit order and install | 30 days | Day 26 | Space plan and seating |
| Prepare | Fit-out and furniture | 25 days | Day 56 | Internet circuit order and install |
| Prepare | Network and Wi-Fi setup | 5 days | Day 81 | Fit-out and furniture |
| Prepare | Movers booked | 2 days | Day 86 | Network and Wi-Fi setup |
| Communicate | Staff communication and packing guide | 3 days | Day 88 | Movers booked |
| Communicate | Address change notices | 5 days | Day 91 | Staff communication and packing guide |
| Move | Packing and labeling | 3 days | Day 96 | Address change notices |
| Move | Move weekend | 2 days | Day 99 | Packing and labeling |
| Move | IT setup and testing | 2 days | Day 101 | Move weekend |
| Settle | Post-move support | 5 days | Day 103 | IT setup and testing |
| Settle | Old office handover | 5 days | Day 108 | Post-move support |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this office move plan
Office moves are often paced by internet and network installation, which can take weeks to provision. This plan starts the circuit order early and keeps it visible.
It fits a small or mid-size office moving to one new location.
Who it's for: Office managers, operations leads and IT managers.
How to use it
- Open the plan. Click Use this template.
- Start the circuit order early. Unlink the internet install and start it as soon as the lease is signed. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Set the move date. Set the first task's start date, then adjust durations until move weekend lands on your planned date.
- Share with staff. Share a read-only link so everyone knows packing and move dates.
Planning tips
- Ask your provider for the circuit install lead time before you pick a move date.
- Label everything by seat number from the space plan.
- Keep the old office handover date in the plan; leases often specify it.
Frequently asked questions
- How long does an office move take to plan?
- Often a few months once the lease is signed, depending mostly on fit-out and network installation. This template spans three to four months.
- Can I share the plan with vendors?
- Yes, with a read-only link that needs no account.
- Can I export to PDF for leadership?
- CSV downloads and print to PDF from your browser are on Solo ($12/month).
Related templates and guides
- Construction Schedule Gantt chart template
- Employee Onboarding Plan Gantt chart template
- ERP Implementation Plan Gantt chart template
- Warehouse Relocation Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.