Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 13 tasks across 3 phases, about 22 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Acquire | Detailed inspection and scope | 3 days | Day 1 | Nothing (starts first) |
| Acquire | Budget and contractor bids | 7 days | Day 4 | Detailed inspection and scope |
| Acquire | Purchase closing | 30 days | Day 11 | Budget and contractor bids |
| Renovate | Permits | 14 days | Day 41 | Purchase closing |
| Renovate | Demolition | 3 days | Day 55 | Permits |
| Renovate | Structural and systems repairs | 10 days | Day 58 | Demolition |
| Renovate | Drywall and paint | 7 days | Day 68 | Structural and systems repairs |
| Renovate | Kitchen and bathroom updates | 14 days | Day 75 | Drywall and paint |
| Renovate | Flooring and fixtures | 7 days | Day 89 | Kitchen and bathroom updates |
| Sell | Final cleaning and staging | 3 days | Day 96 | Flooring and fixtures |
| Sell | Listing photos and listing | 3 days | Day 99 | Final cleaning and staging |
| Sell | Showings and offers | 21 days | Day 102 | Listing photos and listing |
| Sell | Sale closing | 30 days | Day 123 | Showings and offers |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this house flip plan
Every week a flip takes adds holding costs such as loan interest, taxes and utilities. A timeline makes those weeks visible and shows which delays — permits, contractor availability, inspections — push out the sale.
It fits a cosmetic-to-moderate renovation of a single-family home.
Who it's for: Real estate investors, flippers and renovation contractors.
How to use it
- Open the plan. Click Use this template.
- Use real timelines. Replace the closing and permit durations with what your lender and permit office tell you.
- Watch holding time. Use the total duration to estimate holding costs for your budget.
- Share with your team. Send a read-only link to your contractor, agent and partners.
Planning tips
- Get bids before closing so work can start right away.
- Choose finishes that suit the neighborhood's buyers.
- Include the sale closing period in your holding-cost estimate.
Frequently asked questions
- How long does a house flip take?
- This template totals about five months from purchase to sale closing in sequence.
- Is this financial advice?
- No. It is a scheduling template; costs and timelines vary by market.
- Is it free?
- Yes. Opening and editing the template is free.
Related templates and guides
- Home Renovation Plan Gantt chart template
- Kitchen Remodel Timeline Gantt chart template
- Bathroom Remodel Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.