Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 18 tasks across 4 phases, about 13 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Design | Measure and layout | 3 days | Day 1 | Nothing (starts first) |
| Design | Cabinet and appliance selection | 7 days | Day 4 | Measure and layout |
| Design | Order cabinets | 2 days | Day 11 | Cabinet and appliance selection |
| Design | Cabinet lead time | 35 days | Day 13 | Order cabinets |
| Prep | Set up temporary kitchen | 1 day | Day 48 | Cabinet lead time |
| Prep | Demolition | 3 days | Day 49 | Set up temporary kitchen |
| Prep | Plumbing and electrical rough-in | 5 days | Day 52 | Demolition |
| Prep | Inspection | 2 days | Day 57 | Plumbing and electrical rough-in |
| Build | Drywall patch and paint | 4 days | Day 59 | Inspection |
| Build | Flooring | 3 days | Day 63 | Drywall patch and paint |
| Build | Base and wall cabinet install | 4 days | Day 66 | Flooring |
| Build | Countertop templating | 1 day | Day 70 | Base and wall cabinet install |
| Build | Countertop fabrication | 10 days | Day 71 | Countertop templating |
| Build | Countertop install | 1 day | Day 81 | Countertop fabrication |
| Finish | Sink, faucet and appliance hookup | 2 days | Day 82 | Countertop install |
| Finish | Backsplash tile | 3 days | Day 84 | Sink, faucet and appliance hookup |
| Finish | Lighting and trim | 2 days | Day 87 | Backsplash tile |
| Finish | Punch list | 2 days | Day 89 | Lighting and trim |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this kitchen remodel timeline
Kitchens have a fixed order that is easy to get wrong. Countertops can't be templated until base cabinets are installed and level, and the backsplash goes on after the countertops are set. Cabinet lead time often decides the whole schedule, so ordering starts at the top of this plan.
The template assumes the room keeps its footprint with some plumbing and electrical changes. If you are moving walls, add a structural step after demolition.
Who it's for: Homeowners, kitchen designers and remodeling contractors.
How to use it
- Open the timeline. Click Use this template. The remodel loads with cabinet lead time as the longest bar.
- Enter your supplier lead time. Replace the 35-day cabinet lead time with the date your supplier quoted, so the kitchen isn't torn out longer than needed.
- Overlap prep with lead time. Unlink demolition from the lead-time bar and slide it to finish just before cabinets arrive. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Share with your installer. Send a read-only link so the installer, fabricator and tile setter see the same sequence.
Planning tips
- Don't demolish until cabinets have a confirmed ship date.
- Countertop fabrication starts only after templating, so keep those two as separate bars.
- Set up a temporary kitchen before demolition; plan for a stretch without a working sink.
Frequently asked questions
- What is the order of a kitchen remodel?
- Design and order, demolition, rough-in and inspection, drywall and flooring, cabinets, countertop templating and install, plumbing and appliance hookup, backsplash, then trim and punch list.
- Why is countertop install separate from templating?
- Fabricators measure the installed cabinets first, then cut the slab. The gap between templating and install is real waiting time and belongs on the schedule.
- Can I print this timeline?
- Viewing and sharing are free. CSV downloads and print to PDF from your browser are part of the Solo plan at $12/month.
Related templates and guides
- Home Renovation Plan Gantt chart template
- Construction Schedule Gantt chart template
- Restaurant Opening Plan Gantt chart template
- Construction scheduling with a Gantt chart
- Microsoft Project alternative for schedules
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.