Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 17 tasks across 5 phases, about 7 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Plan | Layout and budget | 3 days | Day 1 | Nothing (starts first) |
| Plan | Tile, vanity and fixture selections | 7 days | Day 4 | Layout and budget |
| Plan | Permit if required | 10 days | Day 11 | Tile, vanity and fixture selections |
| Plan | Order vanity and fixtures | 3 days | Day 21 | Permit if required |
| Demo | Demolition and haul-away | 2 days | Day 24 | Order vanity and fixtures |
| Demo | Subfloor and framing repairs | 2 days | Day 26 | Demolition and haul-away |
| Rough-in | Plumbing rough-in | 2 days | Day 28 | Subfloor and framing repairs |
| Rough-in | Electrical and exhaust fan rough-in | 2 days | Day 30 | Plumbing rough-in |
| Rough-in | Rough-in inspection | 2 days | Day 32 | Electrical and exhaust fan rough-in |
| Build | Cement board and drywall | 2 days | Day 34 | Rough-in inspection |
| Build | Shower waterproofing | 2 days | Day 36 | Cement board and drywall |
| Build | Tile floor and walls | 5 days | Day 38 | Shower waterproofing |
| Build | Grout and seal | 2 days | Day 43 | Tile floor and walls |
| Finish | Paint | 2 days | Day 45 | Grout and seal |
| Finish | Vanity, toilet and fixtures | 2 days | Day 47 | Paint |
| Finish | Mirror, lighting and accessories | 1 day | Day 49 | Vanity, toilet and fixtures |
| Finish | Final inspection and walkthrough | 1 day | Day 50 | Mirror, lighting and accessories |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this bathroom remodel
A bathroom packs plumbing, electrical, ventilation, waterproofing and tile into a small room, so trades queue behind each other. The order matters: rough-in and inspection, then the waterproofing layer behind the shower, then tile, then fixtures. This template keeps that order and leaves room for grout and sealant cure time.
It suits a full gut remodel of one bathroom. For a cosmetic refresh with no plumbing moves, delete the rough-in and inspection rows.
Who it's for: Homeowners planning with a contractor, and remodelers who want a clear schedule for clients.
How to use it
- Open the plan. Click Use this template. The remodel opens as a live Gantt chart.
- Order fixtures early. Keep the order row in the planning phase; a backordered vanity can stop the job at the end.
- Respect cure times. Use the waterproofing and grout rows to hold the manufacturer's cure times before the next trade.
- Share with the contractor. Send a read-only link so everyone works from the same dates.
Planning tips
- Check whether your jurisdiction needs a permit for plumbing or electrical changes.
- Have fixtures on site before demolition starts.
- Plan for a second bathroom or alternative while this one is out of service.
Frequently asked questions
- How long does a bathroom remodel take?
- This template totals a little over seven weeks including planning and permit time. The construction rows total 27 days, about four calendar weeks.
- Why is waterproofing its own task?
- Tile and grout aren't waterproof by themselves; a membrane behind the tile protects the walls. It needs its own time to install and cure.
- Can I download the schedule?
- Sharing is free. PDF and CSV downloads are on Solo ($12/month).
Related templates and guides
- Kitchen Remodel Timeline Gantt chart template
- Home Renovation Plan Gantt chart template
- Construction Schedule Gantt chart template
- Construction scheduling with a Gantt chart
- Microsoft Project alternative for schedules
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.