Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 13 tasks across 4 phases, about 22 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Discovery | Requirements and user stories | 7 days | Day 1 | Nothing (starts first) |
| Discovery | UX flows and wireframes | 10 days | Day 8 | Requirements and user stories |
| Discovery | Visual design | 10 days | Day 18 | UX flows and wireframes |
| Build | Backend API and data model | 25 days | Day 28 | Visual design |
| Build | iOS build | 30 days | Day 53 | Backend API and data model |
| Build | Android build | 30 days | Day 83 | iOS build |
| Build | Analytics and crash reporting | 3 days | Day 113 | Android build |
| Test | Internal QA | 10 days | Day 116 | Analytics and crash reporting |
| Test | Beta testing | 14 days | Day 126 | Internal QA |
| Test | Fixes from beta feedback | 7 days | Day 140 | Beta testing |
| Release | Store listings and screenshots | 3 days | Day 147 | Fixes from beta feedback |
| Release | App store submission and review | 7 days | Day 150 | Store listings and screenshots |
| Release | Public launch | 1 day | Day 157 | App store submission and review |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this mobile app development plan
Building the app is only part of the schedule. Beta testing, store listing assets and app store review all sit between 'feature complete' and 'available to download'. This plan includes them.
It assumes one team building an iOS and an Android app against a shared backend.
Who it's for: Startup founders, product managers and development agencies.
How to use it
- Open the plan. Click Use this template.
- Parallelize the platforms. Unlink the iOS and Android builds so they run side by side once the API contract is set. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Add your features. Break each build bar into the features you are shipping.
- Share with stakeholders. Share a read-only link with investors or clients.
Planning tips
- Lock the API contract early so mobile builds aren't waiting on backend changes.
- Store review times vary; leave buffer before any announced launch date.
- Prepare store screenshots during beta, not after.
Frequently asked questions
- How do I plan an app development timeline?
- Start with discovery and design, build the backend and clients in parallel, then budget for QA, beta, fixes and store review before launch.
- Can I plan sprints inside this timeline?
- Yes. Split the build bars into sprints, or use the software sprint template for each one.
- Can I export the timeline for a client?
- Read-only sharing is free; CSV downloads and print to PDF from your browser are on Solo ($12/month).
Related templates and guides
- Software Sprint Plan Gantt chart template
- Website Redesign Plan Gantt chart template
- Data Migration Plan Gantt chart template
- Microsoft Project alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.