Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 5 phases, about 13 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Discovery | Stakeholder interviews and goals | 5 days | Day 1 | Nothing (starts first) |
| Discovery | Analytics and content audit | 5 days | Day 6 | Stakeholder interviews and goals |
| Discovery | Sitemap and page inventory | 3 days | Day 11 | Analytics and content audit |
| Design | Wireframes | 7 days | Day 14 | Sitemap and page inventory |
| Design | Visual design | 10 days | Day 21 | Wireframes |
| Design | Design review and sign-off | 3 days | Day 31 | Visual design |
| Content | Copywriting | 14 days | Day 34 | Design review and sign-off |
| Content | Imagery and assets | 7 days | Day 48 | Copywriting |
| Build | Front-end development | 15 days | Day 55 | Imagery and assets |
| Build | CMS setup and content entry | 7 days | Day 70 | Front-end development |
| Build | Redirect map from old URLs | 2 days | Day 77 | CMS setup and content entry |
| Launch | QA, accessibility and performance checks | 5 days | Day 79 | Redirect map from old URLs |
| Launch | Launch | 1 day | Day 84 | QA, accessibility and performance checks |
| Launch | Post-launch fixes and monitoring | 7 days | Day 85 | Launch |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this website redesign plan
Redesigns run late for two predictable reasons: content arrives after design is finished, and redirects from old URLs are forgotten until search traffic drops. This plan gives both their own rows.
It fits a marketing site of a few dozen pages built by a small team or agency.
Who it's for: Marketing teams, web agencies and freelancers.
How to use it
- Open the plan. Click Use this template to load the redesign as a Gantt.
- Overlap content and design. Unlink copywriting from design so it starts as soon as the sitemap is set. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Assign client and agency owners. Use owners to show which tasks wait on the client, such as content and sign-offs.
- Share a read-only link. Clients see progress without logging in.
Planning tips
- Write the redirect map before launch; changed URLs without redirects lose search traffic.
- Content is the most common blocker; start it early.
- Include accessibility checks in QA rather than after launch.
Frequently asked questions
- How long does a website redesign take?
- It depends on page count, content readiness and approvals. This template runs roughly three months; adjust it to your scope.
- What should a website redesign project plan include?
- Discovery, information architecture, content, design, development, redirects, QA and post-launch monitoring, with an owner for each.
- Can clients see the plan?
- Yes. Share a read-only link; clients do not need an account.
Related templates and guides
- Marketing Launch Plan Gantt chart template
- Software Sprint Plan Gantt chart template
- Mobile App Development Plan Gantt chart template
- Marketing campaign timeline maker
- Product launch roadmap
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.