Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 4 phases, about 28 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Manuscript | Self-revision | 21 days | Day 1 | Nothing (starts first) |
| Manuscript | Developmental edit | 30 days | Day 22 | Self-revision |
| Manuscript | Revisions | 21 days | Day 52 | Developmental edit |
| Manuscript | Copyedit | 14 days | Day 73 | Revisions |
| Design | Cover design | 21 days | Day 87 | Copyedit |
| Design | Interior layout and ebook formatting | 10 days | Day 108 | Cover design |
| Design | Proofreading | 10 days | Day 118 | Interior layout and ebook formatting |
| Pre-launch | Advance reader copies sent | 1 day | Day 128 | Proofreading |
| Pre-launch | Advance reader period | 30 days | Day 129 | Advance reader copies sent |
| Pre-launch | Retailer listings and pre-order | 3 days | Day 159 | Advance reader period |
| Launch | Launch week promotion | 7 days | Day 162 | Retailer listings and pre-order |
| Launch | Post-launch marketing | 30 days | Day 169 | Launch week promotion |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this book publishing timeline
Self-publishing has more handoffs than most authors expect: editors, a cover designer, a formatter, a proofreader and early readers each need time. This plan sequences them and lets the cover and pre-launch work run while the text is still being edited.
It assumes a finished first draft. Traditionally published authors can use it to track their own deliverables.
Who it's for: Self-publishing authors, small presses and book coaches.
How to use it
- Open the plan. Click Use this template.
- Run cover design alongside editing. Unlink cover design so it starts during the developmental edit. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Book freelancers early. Use the dates to book editors and designers, many of whom schedule weeks ahead.
- Share with your team. Send a read-only link to your editor and designer.
Planning tips
- Proofread after layout, not before; layout introduces its own errors.
- Give early readers enough time to read and review before launch.
- Open pre-orders only once the interior is final.
Frequently asked questions
- How long does it take to self-publish a book?
- From a finished draft, often several months depending on editing rounds and freelancer availability. This template spans six to seven months.
- Can I plan a series?
- Yes. Add rows for each book; Solo saves unlimited projects.
- Is the template free?
- Yes. Opening and editing it is free.
Related templates and guides
- Thesis and Dissertation Timeline Gantt chart template
- Film Production Schedule Gantt chart template
- Grant Proposal Timeline Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.