Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 16 tasks across 4 phases, about 37 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Foundations | Budget and priorities | 7 days | Day 1 | Nothing (starts first) |
| Foundations | Draft guest list | 14 days | Day 8 | Budget and priorities |
| Foundations | Venue tours and booking | 30 days | Day 22 | Draft guest list |
| Vendors | Photographer and videographer | 14 days | Day 52 | Venue tours and booking |
| Vendors | Caterer and menu | 21 days | Day 66 | Photographer and videographer |
| Vendors | Officiant | 7 days | Day 87 | Caterer and menu |
| Vendors | Music or DJ | 14 days | Day 94 | Officiant |
| Vendors | Florist and decor | 14 days | Day 108 | Music or DJ |
| Details | Attire shopping and fittings | 60 days | Day 122 | Florist and decor |
| Details | Save-the-dates | 7 days | Day 182 | Attire shopping and fittings |
| Details | Invitations designed and mailed | 21 days | Day 189 | Save-the-dates |
| Details | RSVP collection | 35 days | Day 210 | Invitations designed and mailed |
| Final | Seating chart | 7 days | Day 245 | RSVP collection |
| Final | Final vendor confirmations | 7 days | Day 252 | Seating chart |
| Final | Rehearsal | 1 day | Day 259 | Final vendor confirmations |
| Final | Wedding day | 1 day | Day 260 | Rehearsal |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this wedding planning timeline
Wedding planning is a dependency chain: the guest count shapes the venue, the venue sets the date, and the date drives every vendor booking. This template follows that chain so you book in the right order.
It covers most of a year of planning. If you have less time, compress the early tasks; the order stays the same.
Who it's for: Couples planning their own wedding and planners who want a clear plan to share with clients.
How to use it
- Open the plan. Click Use this template. No sign-up needed to start editing.
- Set the wedding date. Set the first task to start today, then adjust durations until the wedding day lands on your date. Anything that would run late needs a shorter duration or to run in parallel.
- Split tasks between partners. Use the owner field so each of you knows which bookings are yours.
- Share with family or your planner. Send a read-only link so everyone sees the same dates.
Planning tips
- Settle a guest count range before touring venues; capacity rules out options quickly.
- Attire usually needs several fittings. Leave room before the final one.
- Set the RSVP deadline so it lands before the caterer's headcount deadline.
Frequently asked questions
- What should be on a wedding planning timeline?
- Budget, guest list, venue, key vendors (photography, catering, music, flowers), attire, stationery, RSVPs, seating, final confirmations and the rehearsal.
- Is the template free?
- Yes. Opening and editing the template is free, and a free account saves one project.
- Can I add my own tasks?
- Yes. Click into the chart to add, rename, move or delete any task.
Related templates and guides
- Event Planning Timeline Gantt chart template
- Home Renovation Plan Gantt chart template
- Conference Planning Timeline Gantt chart template
- Event planning timeline
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.