Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 11 tasks across 4 phases, about 9 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Prepare | Prior-year actuals review | 5 days | Day 1 | Nothing (starts first) |
| Prepare | Budget guidelines and templates | 5 days | Day 6 | Prior-year actuals review |
| Prepare | Kickoff with department heads | 1 day | Day 11 | Budget guidelines and templates |
| Submit | Department budget drafts | 15 days | Day 12 | Kickoff with department heads |
| Submit | Headcount and capital requests | 10 days | Day 27 | Department budget drafts |
| Consolidate | Finance consolidation | 7 days | Day 37 | Headcount and capital requests |
| Consolidate | Leadership review meetings | 5 days | Day 44 | Finance consolidation |
| Consolidate | Revisions | 7 days | Day 49 | Leadership review meetings |
| Approve | Final budget approval | 2 days | Day 56 | Revisions |
| Approve | Communicate budgets to departments | 2 days | Day 58 | Final budget approval |
| Approve | Load budget into accounting system | 3 days | Day 60 | Communicate budgets to departments |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this annual budget planning
Budget season runs on deadlines that depend on each other: finance can't consolidate until departments submit, and leadership can't approve until reviews finish. This plan lays out that cycle so department heads know when their inputs are due.
It fits small and mid-sized organizations. Rename the phases to match your fiscal calendar.
Who it's for: Finance managers, controllers, CFOs and nonprofit finance teams.
How to use it
- Open the plan. Click Use this template.
- Anchor the approval date. Set the first task's start date, then adjust durations until final approval lands on your board or leadership date.
- Run requests in parallel. Select headcount and capital requests, remove the predecessor in the task panel, then set its start date to match department drafts.
- Share deadlines. Send a read-only link to every department head.
Planning tips
- Give departments templates with last year's actuals filled in.
- Leave time for a second round of revisions.
- Mark the approval meeting as a milestone.
Frequently asked questions
- When should budget planning start?
- It depends on your fiscal year and approval process. This template spans about two months.
- Can I export the timeline?
- Sharing is free. PDF and CSV downloads are on Solo ($12/month).
- Does this connect to accounting software?
- No. It is a timeline for the budget process, not a budgeting tool.
Related templates and guides
- Compliance Audit Preparation Plan Gantt chart template
- ERP Implementation Plan Gantt chart template
- Grant Proposal Timeline Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.