Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 4 phases, about 13 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Plan | Theme, outline and owners | 5 days | Day 1 | Nothing (starts first) |
| Plan | Request data and stories | 10 days | Day 6 | Theme, outline and owners |
| Content | Year-end financial statements | 21 days | Day 16 | Request data and stories |
| Content | Write narrative sections | 14 days | Day 37 | Year-end financial statements |
| Content | Photos and charts | 7 days | Day 51 | Write narrative sections |
| Design | Layout and design | 10 days | Day 58 | Photos and charts |
| Design | First review round | 5 days | Day 68 | Layout and design |
| Design | Revisions | 5 days | Day 73 | First review round |
| Design | Leadership approval | 3 days | Day 78 | Revisions |
| Publish | Proofreading | 3 days | Day 81 | Leadership approval |
| Publish | Publish online and print | 5 days | Day 84 | Proofreading |
| Publish | Distribute to stakeholders | 3 days | Day 89 | Publish online and print |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this annual report production
An annual report waits on two tracks: the year's numbers and the stories around them. Writing can start before final figures, but design and approvals need both. This plan lists the steps in order, with room for review rounds, so design starts once both the figures and the narrative are ready.
It fits nonprofit impact reports and company annual reviews. Regulated financial filings follow their own rules and deadlines.
Who it's for: Communications teams, finance teams and nonprofit development staff.
How to use it
- Open the plan. Click Use this template.
- Start from the approval date. Adjust durations until leadership approval lands before your publishing date.
- Mark review owners. Name who reviews each round so feedback isn't late.
- Share with contributors. Send a read-only link to everyone supplying content.
Planning tips
- Ask for data and stories early; they are usually the bottleneck.
- Limit review rounds and reviewers.
- Proofread after the final layout, not before.
Frequently asked questions
- How long does an annual report take?
- This template totals about three months in sequence; writing and financials often overlap.
- Can I export the timeline?
- Sharing is free. PDF and CSV downloads are on Solo ($12/month).
- Is it free?
- Yes. Opening and editing the template is free.
Related templates and guides
- Annual Budget Planning Gantt chart template
- Compliance Audit Preparation Plan Gantt chart template
- Book Publishing Timeline Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.