Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 4 phases, about 17 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Development | Script lock | 14 days | Day 1 | Nothing (starts first) |
| Development | Budget and schedule | 7 days | Day 15 | Script lock |
| Pre-production | Casting | 14 days | Day 22 | Budget and schedule |
| Pre-production | Location scouting and permits | 14 days | Day 36 | Casting |
| Pre-production | Crew hiring | 10 days | Day 50 | Location scouting and permits |
| Pre-production | Shot list and storyboards | 7 days | Day 60 | Crew hiring |
| Pre-production | Table read and rehearsals | 3 days | Day 67 | Shot list and storyboards |
| Production | Principal photography | 5 days | Day 70 | Table read and rehearsals |
| Production | Pickups and b-roll | 2 days | Day 75 | Principal photography |
| Post-production | Editorial through picture lock | 21 days | Day 77 | Pickups and b-roll |
| Post-production | Music and sound design | 10 days | Day 98 | Editorial through picture lock |
| Post-production | Color grade | 5 days | Day 108 | Music and sound design |
| Post-production | Sound mix | 3 days | Day 113 | Color grade |
| Post-production | Deliverables and captions | 3 days | Day 116 | Sound mix |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this film production schedule
Short films, commercials and documentaries follow the same arc: pre-production locks the script, cast, crew and locations; production captures the footage; post-production edits, grades, mixes and delivers. Post is easy to underestimate, so it gets detailed rows here.
Durations fit a short film or branded video with a handful of shoot days.
Who it's for: Producers, independent filmmakers and video agencies.
How to use it
- Open the schedule. Click Use this template.
- Run pre-production tracks in parallel. Unlink casting, locations and crew so they run at the same time after script lock. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Split the shoot by day. Break principal photography into individual shoot days by location.
- Share with the crew. Send a read-only link to department heads.
Planning tips
- Location permits can take longer than casting; start them early.
- Music licensing and sound design can start before picture lock.
- Confirm caption and delivery specs at the start, not at the end.
Frequently asked questions
- What are the stages of film production?
- Development, pre-production, production (the shoot) and post-production (edit, sound, color, delivery).
- Can I schedule individual shoot days?
- Yes. Split the production row into one bar per day or location.
- Can I export the schedule?
- CSV downloads and print to PDF from your browser are on Solo ($12/month).
Related templates and guides
- Book Publishing Timeline Gantt chart template
- Marketing Launch Plan Gantt chart template
- Event Planning Timeline Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.