Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 18 tasks across 7 phases, about 15 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Proposal | Problem statement and team charter | 5 days | Day 1 | Nothing (starts first) |
| Proposal | Proposal draft | 7 days | Day 6 | Problem statement and team charter |
| Proposal | Advisor proposal approval | 7 days | Day 13 | Proposal draft |
| Research | Literature and prior work review | 12 days | Day 13 | Proposal draft |
| Research | Requirements and success criteria | 6 days | Day 20 | Advisor proposal approval |
| Design | Concept options and selection | 8 days | Day 26 | Requirements and success criteria, Literature and prior work review |
| Design | Detailed design | 10 days | Day 34 | Concept options and selection |
| Design | Design review with advisor | 3 days | Day 44 | Detailed design |
| Implementation | Build iteration 1 | 15 days | Day 47 | Design review with advisor |
| Implementation | Midpoint demo | 1 day | Day 62 | Build iteration 1 |
| Implementation | Build iteration 2 | 15 days | Day 63 | Midpoint demo |
| Validation | Testing against success criteria | 8 days | Day 78 | Build iteration 2 |
| Validation | User or client feedback | 5 days | Day 63 | Midpoint demo |
| Report | Report: background and design chapters | 10 days | Day 47 | Design review with advisor |
| Report | Report: results and evaluation | 7 days | Day 86 | Testing against success criteria |
| Report | Advisor draft review | 7 days | Day 93 | Report: results and evaluation, Report: background and design chapters |
| Report | Final edits and poster | 5 days | Day 100 | Advisor draft review |
| Defense | Final presentation and demo | 1 day | Day 105 | Final edits and poster |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 105 days instead of the 132 it would take one task at a time. The 15 darker bars are the critical path: a day lost on any of them moves the finish date.
About this capstone project
A capstone is long enough that a plan matters and short enough that one slipped month is fatal. Most capstone teams lose time in two places: waiting for proposal approval, and treating the report as something to write after the work is done. This template plans around both, starting the literature review while the proposal is being reviewed and writing the report in parallel with implementation.
It fits an engineering, computer science, information systems or business capstone run over two semesters with a team of three to five and a faculty advisor. Advisor reviews are tasks in their own right, because they depend on someone else's calendar.
If your programme runs the capstone over one semester, keep the structure and halve the build and test durations.
Who it's for: Capstone teams, senior design students and the faculty advisors who supervise them.
How to use it
- Use this template. Click Use this template to open the capstone plan in the editor. No account is needed to start.
- Put in your term dates. Move the first task to your start date and the final presentation to your programme's date. Check whether the critical path fits between them.
- Book advisor reviews. Ask your advisor for the review dates now and set the review tasks on them. Everything that depends on approval moves with them.
- Share it. Share a read-only link with your advisor and sponsor. A link is a snapshot, so send a new one after each review.
Why the report is written alongside the work
In this template the background and design chapters start as soon as the design review is done, while implementation is under way. The results chapter waits for testing. That split means the advisor draft review can happen with most of the report already written, and the last weeks are spent on results and polish rather than on writing a whole report from memory.
The midpoint demo is a one-day milestone after the first build iteration. It gives you a fixed point to show progress and collect feedback from users or a client, and the feedback task runs beside the second build iteration so changes can be made before final testing.
Showing your advisor the critical path
Advisors often ask what happens if something slips. With the dependencies in place, you can drag a task in the editor and show exactly which later tasks move and whether the final presentation is at risk. The darker bars on this page are the tasks with no slack in the example durations.
Planning tips
- Write your success criteria early; testing and the evaluation chapter are much easier when you know what you are testing against.
- Keep a shared log of decisions and why you made them. It becomes the design rationale section of the report.
- Plan two build iterations rather than one, so there is a working version at the midpoint.
- Print the poster early. Printing services get busy at the end of term.
Frequently asked questions
- What should a capstone project Gantt chart include?
- The proposal and its approval, research or literature review, requirements, design and design review, implementation, testing, the written report with advisor reviews, and the final presentation or defense. This template includes all of these with their dependencies.
- How long is a capstone project?
- Most capstones run one or two semesters. This template is about seven months of calendar time; scale the durations to your programme.
- Can my whole team edit the plan?
- Each person can open the template in their own browser. To work on one shared plan, one team member saves it to their account and shares a read-only link with the others, who send updates to that person.
- Is it free?
- Yes. The template opens without an account, and the free plan saves one project.
Related templates and guides
- Student Project Plan Gantt chart template
- Thesis and Dissertation Timeline Gantt chart template
- Research Project Plan Gantt chart template
- Engineering Design Project Gantt chart template
- Gantt chart in Google Sheets
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.