Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 17 tasks across 6 phases, about 13 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Define | Requirements specification | 8 days | Day 1 | Nothing (starts first) |
| Define | Risk assessment | 4 days | Day 9 | Requirements specification |
| Concept | Concept generation | 8 days | Day 9 | Requirements specification |
| Concept | Concept analysis and trade study | 7 days | Day 17 | Concept generation |
| Concept | Preliminary design review | 2 days | Day 24 | Concept analysis and trade study, Risk assessment |
| Design | Detailed mechanical design | 15 days | Day 26 | Preliminary design review |
| Design | Detailed electrical design | 15 days | Day 26 | Preliminary design review |
| Design | Simulation and calculations | 8 days | Day 41 | Detailed mechanical design |
| Design | Critical design review | 2 days | Day 49 | Simulation and calculations, Detailed electrical design |
| Prototype | Long-lead parts order | 20 days | Day 26 | Preliminary design review |
| Prototype | Prototype parts fabrication | 12 days | Day 51 | Critical design review |
| Prototype | Prototype assembly | 5 days | Day 63 | Prototype parts fabrication, Long-lead parts order |
| Verify | Verification test plan | 5 days | Day 51 | Critical design review |
| Verify | Verification testing | 10 days | Day 68 | Prototype assembly, Verification test plan |
| Verify | Design changes from testing | 7 days | Day 78 | Verification testing |
| Release | Drawings and documentation | 6 days | Day 85 | Design changes from testing |
| Release | Design release | 1 day | Day 91 | Drawings and documentation |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 91 days instead of the 135 it would take one task at a time. The 13 darker bars are the critical path: a day lost on any of them moves the finish date.
About this engineering design project
Engineering projects are paced by reviews and prototypes. A concept that fails the preliminary design review sends the team back to analysis; a prototype that fails verification sends it back to detailed design. This template makes those loops visible by putting each review and each build-and-test cycle on the plan as its own task with its own dependencies.
It is written for a mechanical, electrical or mechatronic design project with one prototype iteration, run by a small engineering team over about five months. The structure follows the common sequence of requirements, concept, preliminary design review, detailed design, critical design review, prototype and verification.
If you are bringing the finished design into production, continue with the manufacturing production plan template, which starts where this one ends.
Who it's for: Engineering leads, project engineers and students on engineering design courses.
How to use it
- Use this template. Click Use this template. Requirements, concept, design, prototype, verification and release open as lanes with the reviews linked as gates.
- Split the design work. Mechanical and electrical design run in parallel. Add firmware, software or other disciplines as extra parallel tasks, each linked to the critical design review.
- Order long-lead parts early. The long-lead parts order starts after the preliminary design review on purpose. Change its duration to your supplier's lead time and check whether it reaches the critical path.
- Use the chart in reviews. Share a read-only link before each design review so reviewers see the schedule impact of any action they raise.
Design reviews as schedule gates
The preliminary design review (PDR) and critical design review (CDR) are two-day tasks that everything downstream waits for. In practice they are often followed by actions; if your reviews usually produce rework, add a short action-closure task after each one and link the next phase to it.
Mechanical and electrical design run side by side after the PDR, and the CDR waits for both. That is where integration problems surface, which is why simulation sits on the mechanical path before the review.
The prototype loop
This template plans one prototype and one round of design changes. If your product normally needs two prototypes, duplicate the fabrication, assembly, testing and design-change tasks and link the second set after the first. The finish date will tell you whether a second loop fits.
Planning tips
- Write requirements that can be verified; every requirement should map to a test in the verification plan.
- Start the verification test plan at CDR so test fixtures are ready when the prototype is.
- Keep supplier quotes and dates in the task description so the reason for a date is never lost.
- Save a baseline after the PDR and compare against it at the CDR.
Frequently asked questions
- What is the engineering design process on a Gantt chart?
- Requirements, concept generation and selection, preliminary design review, detailed design, critical design review, prototype build, verification testing and design release. Each stage is a group of tasks linked to the review or test before it.
- Can I show parallel engineering disciplines?
- Yes. Mechanical and electrical design already run in parallel in this template. Add other disciplines as tasks that start after the preliminary design review and finish before the critical design review.
- Does it show the critical path?
- Yes. The darker bars on this page are the critical path for the example durations, and the editor recalculates it when you change a duration or link.
- Can I import my existing schedule?
- The editor imports Microsoft Project XML and CSV files. You can also paste a task list from a spreadsheet.
Related templates and guides
- Manufacturing Production Plan Gantt chart template
- Manufacturing New Product Introduction Gantt chart template
- Equipment Installation and Commissioning Gantt chart template
- Capstone Project Gantt chart template
- Microsoft Project alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.