Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 15 tasks across 5 phases, about 6 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Start | Choose topic and agree roles | 2 days | Day 1 | Nothing (starts first) |
| Start | Project proposal | 3 days | Day 3 | Choose topic and agree roles |
| Start | Teacher feedback on proposal | 3 days | Day 6 | Project proposal |
| Research | Background reading and sources | 8 days | Day 9 | Teacher feedback on proposal |
| Research | Survey or experiment design | 4 days | Day 9 | Teacher feedback on proposal |
| Research | Data collection | 7 days | Day 13 | Survey or experiment design |
| Build | Prototype, model or analysis | 8 days | Day 20 | Data collection |
| Build | Results and charts | 4 days | Day 28 | Prototype, model or analysis |
| Write | Report outline | 2 days | Day 17 | Background reading and sources |
| Write | Draft introduction and method | 5 days | Day 19 | Report outline |
| Write | Draft results and discussion | 5 days | Day 32 | Results and charts, Draft introduction and method |
| Write | References and appendix | 2 days | Day 37 | Draft results and discussion |
| Finish | Slides and presentation practice | 4 days | Day 32 | Results and charts |
| Finish | Group review and edits | 3 days | Day 39 | References and appendix, Slides and presentation practice |
| Finish | Submit and present | 1 day | Day 42 | Group review and edits |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 42 days instead of the 61 it would take one task at a time. The 11 darker bars are the critical path: a day lost on any of them moves the finish date.
About this student project plan
Many courses ask for a Gantt chart with a project proposal, and most student plans fail the same way: everything is scheduled for the week before the deadline. This template spreads the work out, lets research and writing overlap, and leaves a review buffer before submission so a late group member does not sink the grade.
It fits a six- to eight-week group project such as a science fair entry, a design and technology project, a business studies report or a coursework assignment with a presentation. Each task has a clear output, which makes it easy to split the work between group members.
If you are planning a final-year capstone, a dissertation or a thesis, use the capstone project or thesis templates instead; they have longer research phases and supervisor reviews.
Who it's for: Students working alone or in groups, and teachers who want to show a class what a realistic project plan looks like.
How to use it
- Use this template. Click Use this template. The plan opens in your browser with no account needed, and every task already waits for what it depends on.
- Set your deadline. Drag the final task to your submission date and move the first task to today. If the plan does not fit, shorten tasks with slack before cutting the review buffer.
- Split the work. Put a group member's name in the owner field of each task. Everyone can see who is doing what.
- Share with your teacher. Copy a read-only share link to include with your proposal; your teacher can open it without an account. Or take a screenshot of the chart for your report.
How to explain your Gantt chart in a proposal
Teachers usually want to see three things: that you have listed the main tasks, that you know which tasks depend on others, and that you have left time to review. In this template the critical path runs from the proposal through data collection, the analysis and the results write-up to the final review. You can say that in one sentence in your proposal and point to the darker bars.
Background reading and the report outline run in parallel with designing the survey or experiment, which is realistic: you will read while you plan. Writing the introduction and method can start before your results exist, so the last week is for results, discussion and polishing, not for writing everything at once.
Making it fit a shorter or longer project
For a two- or three-week assignment, halve each duration but keep the review step. For a term-long project, add a checkpoint with your teacher in the middle of the build phase and link the draft results to it.
Planning tips
- Agree roles on day one and write them in the owner field, so nobody is surprised later.
- Collect your references as you read; rebuilding a reference list at the end takes far longer than you expect.
- Practise the presentation at least once with a timer.
- Keep two or three days of buffer before the deadline for illness, printing problems or a missing section.
Frequently asked questions
- How do I make a Gantt chart for a school project?
- List every task from choosing a topic to submitting, estimate how many days each takes, then link each task to the one it depends on. This template does that for a typical project; change the tasks and dates to match yours.
- Is it free for students?
- Yes. The template opens in the editor without an account. A free account saves one project, which is enough for a school project.
- Can I put the Gantt chart in my report?
- Yes. Take a screenshot of the chart, or share a read-only link. Printing to PDF and CSV downloads from the editor are part of the Solo plan.
- What if my group has different deadlines for each part?
- Move each task to its own deadline. Dependencies keep the order right, and the chart shows if one part's deadline is too close to the next.
Related templates and guides
- Capstone Project Gantt chart template
- Thesis and Dissertation Timeline Gantt chart template
- Research Project Plan Gantt chart template
- Curriculum Development Plan Gantt chart template
- Gantt chart in Google Sheets
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.