Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 17 tasks across 5 phases, about 7 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Owner | Duration | Starts | Depends on |
|---|---|---|---|---|---|
| Prepare | Define the change and the case for it | Sponsor | 4 days | Day 1 | Nothing (starts first) |
| Prepare | Stakeholder and impact assessment | Change manager | 5 days | Day 5 | Define the change and the case for it |
| Prepare | Change readiness survey | HR business partner | 5 days | Day 5 | Define the change and the case for it |
| Prepare | Sponsor and leadership alignment | Sponsor | 2 days | Day 10 | Stakeholder and impact assessment |
| Plan | Recruit change champions | Change manager | 4 days | Day 12 | Sponsor and leadership alignment |
| Plan | Communication plan | Communications lead | 4 days | Day 10 | Stakeholder and impact assessment, Change readiness survey |
| Plan | Training needs analysis | Training lead | 3 days | Day 10 | Stakeholder and impact assessment |
| Plan | Resistance management plan | HR business partner | 3 days | Day 12 | Change readiness survey, Sponsor and leadership alignment |
| Communicate and train | Leadership announcement | Sponsor | 1 day | Day 14 | Communication plan, Sponsor and leadership alignment |
| Communicate and train | Manager briefings and talking points | Communications lead | 3 days | Day 15 | Leadership announcement, Resistance management plan |
| Communicate and train | Build training materials | Training lead | 8 days | Day 13 | Training needs analysis |
| Communicate and train | Deliver training sessions | Training lead | 10 days | Day 21 | Build training materials, Manager briefings and talking points |
| Adopt | Go-live of the new way of working | Milestone | Day 31 | Deliver training sessions | |
| Adopt | Floor support and office hours | Change champions | 10 days | Day 31 | Go-live of the new way of working, Recruit change champions |
| Adopt | Adoption review | Change manager | 2 days | Day 41 | Floor support and office hours |
| Reinforce | Recognise early adopters and fix blockers | Sponsor | 5 days | Day 43 | Adoption review |
| Reinforce | Hand over to business as usual | Change manager | 2 days | Day 48 | Recognise early adopters and fix blockers |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 49 days instead of the 71 it would take one task at a time. The 10 darker bars are the critical path: a day lost on any of them moves the finish date.
About this change management plan
A new system, process or structure can be delivered on time and still fail because people keep working the old way. A change management plan is the part of the project that deals with that: who is affected, what they need to hear and learn, who they hear it from, and how the change is reinforced once it is live.
This template lays that work out as a Gantt chart of about seven weeks, with owners for each task: sponsor, change manager, HR business partner, communications lead, training lead and a network of change champions. It starts with defining the change and assessing the impact, runs communications and training in parallel, and keeps going after go-live with floor support, an adoption review and reinforcement, which is where many plans stop too early.
Link it to your delivery plan by making the go-live milestone here wait for the same date as the technical go-live. If the system slips, the training and the announcement move with it instead of happening weeks before anyone can use what they learned.
Who it's for: Change managers, HR and transformation leads, and project managers who are responsible for adoption, not just delivery.
How to use it
- Use this template. Click Use this template. The plan opens in the editor with prepare, plan, communicate and train, adopt and reinforce as lanes and an owner on every task. No sign-up is needed.
- Describe the change and who it hits. Rename the first tasks to your change and run the impact assessment by group: who does their job differently, and how much. That list drives every communication and training task after it.
- Tie go-live to the delivery plan. Set the go-live milestone to the same date as the technical go-live. Training should finish just before people need it, so check that the gap between the two is days, not weeks.
- Keep the plan running after go-live. Do not close the plan at go-live. Floor support, the adoption review and reinforcement are where you find out whether the change has stuck; share a read-only link so the sponsor sees that work too.
How this plan maps to the ADKAR model
Prosci describes its ADKAR model as a model for individual change, built from five outcomes a person needs: Awareness, Desire, Knowledge, Ability and Reinforcement. It is a useful check on a change plan, because each outcome needs work scheduled for it.
In this template, the leadership announcement and manager briefings build awareness; sponsor alignment, champions and the resistance plan work on desire; training needs analysis and training materials provide knowledge; training sessions and floor support build ability; and the adoption review and recognition step are the reinforcement. If one of the five has no task on your version of the plan, that is the gap to fill.
Sequencing communication and training
People should hear about a change from their sponsor and their own manager before they hear it in a training room. That is why the manager briefings wait for both the leadership announcement and the resistance management plan here: managers get the talking points, including answers to the objections the readiness survey surfaced, before their teams ask.
The critical path runs through the impact assessment, training needs analysis, training materials and training delivery to go-live, then floor support, the adoption review and reinforcement. Communications have three days of slack, so a delayed announcement is not yet a problem, but a delay in building training materials moves go-live support for everyone.
Planning tips
- Segment the impact assessment by group. One message for the whole organisation is usually too vague for the people most affected.
- Let the sponsor announce, and managers explain. People want to hear why from the top and what it means for them from their own manager.
- Schedule training as close to go-live as you can. Training delivered a month early is mostly forgotten by the time it is needed.
- Give the change champions a real task and a date, such as floor support in the first two weeks, not just a title.
- Measure adoption, not attendance. The adoption review should look at whether people use the new way of working, not how many sat the training.
Frequently asked questions
- What should a change management plan include?
- A description of the change and the case for it, a stakeholder and impact assessment, sponsor and leadership roles, a communication plan, training, a way to handle resistance, support after go-live and how the change will be reinforced and measured. Each of those is a linked task in this template.
- When should change management start in a project?
- As early as the project itself. The impact assessment and sponsor alignment take weeks, and communication and training have to be ready before go-live, so starting at the build stage usually means the training is late.
- What is the difference between a change management plan and a communication plan?
- The communication plan is one part of it. The change management plan also covers impact assessment, training, resistance management, support after go-live and reinforcement.
- Can I use this change management plan in Excel?
- Yes. Download CSV gives you every task with its owner, start date, end date, phase and dependencies, which opens in Excel or Google Sheets.
- Is this change management plan template free?
- Yes. Opening and editing it in the browser is free with no sign-up, and the CSV download on this page is free. A free account keeps one saved project.
Related templates and guides
- Implementation Plan Gantt chart template
- Cutover Plan Gantt chart template
- SaaS Customer Implementation Gantt chart template
- Employee Onboarding Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.