Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 4 phases, about 7 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Kickoff | Kickoff call and success criteria | 1 day | Day 1 | Nothing (starts first) |
| Kickoff | Requirements workshop | 5 days | Day 2 | Kickoff call and success criteria |
| Configure | Account configuration | 7 days | Day 7 | Requirements workshop |
| Configure | Customer data export | 5 days | Day 14 | Account configuration |
| Configure | Data import and validation | 5 days | Day 19 | Customer data export |
| Configure | Integrations setup | 7 days | Day 24 | Data import and validation |
| Enable | Admin training | 2 days | Day 31 | Integrations setup |
| Enable | End-user training | 3 days | Day 33 | Admin training |
| Enable | User acceptance testing | 5 days | Day 36 | End-user training |
| Launch | Go-live | 1 day | Day 41 | User acceptance testing |
| Launch | Hypercare support | 10 days | Day 42 | Go-live |
| Launch | Adoption check-in | 1 day | Day 52 | Hypercare support |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this saas customer implementation
Implementations slip when the customer doesn't know what is expected of them: data exports, an admin to configure, people to train. Sharing a timeline from kickoff makes both sides' tasks visible.
Use it for B2B software rollouts that take weeks, not minutes. Mark customer-owned tasks so they're easy to spot.
Who it's for: Implementation managers, customer success teams and consultants.
How to use it
- Open the plan. Click Use this template.
- Assign owners on both sides. Set the owner of each row to your team or the customer's team.
- Share at kickoff. Send a read-only link in the kickoff follow-up.
- Track risks. Mark a task At risk when the customer's input is late so it shows on the chart.
Planning tips
- Agree on success criteria at kickoff and check them at the adoption review.
- Get a sample data export early; import problems are common.
- Train admins before end users.
Frequently asked questions
- Can the customer see the plan without an account?
- Yes. Read-only share links don't need an account.
- Can I download the plan for the customer?
- Sharing a read-only link is free. PDF and CSV downloads are on Solo ($12/month).
- Can I reuse it for every customer?
- Yes. Open the template for each new customer and adjust it.
Related templates and guides
- Cutover Plan Gantt chart template
- RFP Timeline Gantt chart template
- Employee Onboarding Plan Gantt chart template
- ERP Implementation Plan Gantt chart template
- Data Migration Plan Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.