Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 13 tasks across 5 phases, about 37 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Concept | Requirements and cost targets | 14 days | Day 1 | Nothing (starts first) |
| Concept | Concept design | 21 days | Day 15 | Requirements and cost targets |
| Design | Detailed design and drawings | 35 days | Day 36 | Concept design |
| Design | Prototype build | 21 days | Day 71 | Detailed design and drawings |
| Design | Design verification testing | 21 days | Day 92 | Prototype build |
| Industrialize | Supplier selection and quotes | 21 days | Day 113 | Design verification testing |
| Industrialize | Tooling fabrication | 45 days | Day 134 | Supplier selection and quotes |
| Industrialize | First article inspection | 7 days | Day 179 | Tooling fabrication |
| Validate | Pilot production build | 10 days | Day 186 | First article inspection |
| Validate | Production validation testing | 14 days | Day 196 | Pilot production build |
| Validate | Certification testing | 21 days | Day 210 | Production validation testing |
| Ramp | Production ramp | 30 days | Day 231 | Certification testing |
| Ramp | Launch | 1 day | Day 261 | Production ramp |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this manufacturing new product introduction
Hardware schedules are dominated by long, hard-to-compress steps: prototype iterations, tooling and supplier lead times, and validation builds. This template keeps each gate visible so a slip in tooling shows up as a slip in launch.
It suits a physical product moving from design to contract or in-house manufacturing. Rename the gates to your company's stage-gate terms.
Who it's for: Hardware product managers, manufacturing engineers and operations leads.
How to use it
- Open the plan. Click Use this template.
- Run sourcing alongside design. To start supplier selection during detailed design, remove its predecessor in the task panel and set the new start date. Then add design verification testing as a predecessor of tooling fabrication, so a design delay still moves the launch.
- Enter supplier lead times. Replace the tooling duration with your toolmaker's quote; it often sets the launch date.
- Share with suppliers. Send a read-only link so suppliers see the dates that depend on them.
Planning tips
- Plan for more than one prototype round.
- Start certification planning early; test lab slots can book up.
- Keep first article inspection as its own gate.
Frequently asked questions
- What is NPI?
- New product introduction: the process of taking a product from design into reliable volume manufacturing.
- Which certifications should I plan for?
- It depends on the product and markets. Common examples include safety and electromagnetic compatibility testing; check your market's requirements.
- Can the plan run longer than a year?
- Yes. Plans can run up to two years in the editor.
Related templates and guides
- Construction Schedule Gantt chart template
- Product Roadmap Gantt chart template
- Compliance Audit Preparation Plan Gantt chart template
- Microsoft Project alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.