Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 13 tasks across 4 phases, about 17 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Specify | User requirements specification | 10 days | Day 1 | Nothing (starts first) |
| Specify | Vendor quotes and selection | 15 days | Day 11 | User requirements specification |
| Specify | Purchase order | 3 days | Day 26 | Vendor quotes and selection |
| Build | Vendor design review | 5 days | Day 29 | Purchase order |
| Build | Equipment build | 40 days | Day 34 | Vendor design review |
| Build | Factory acceptance test | 3 days | Day 74 | Equipment build |
| Build | Shipping | 7 days | Day 77 | Factory acceptance test |
| Site | Site preparation and utilities | 15 days | Day 84 | Shipping |
| Site | Rigging and installation | 5 days | Day 99 | Site preparation and utilities |
| Site | Site acceptance test | 3 days | Day 104 | Rigging and installation |
| Commission | Commissioning and trial runs | 5 days | Day 107 | Site acceptance test |
| Commission | Operator and maintenance training | 3 days | Day 112 | Commissioning and trial runs |
| Commission | Handover and documentation | 2 days | Day 115 | Operator and maintenance training |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this equipment installation and commissioning
Installing new production equipment has two natural checkpoints: the factory acceptance test (FAT) at the vendor before shipping, and the site acceptance test (SAT) after installation. This plan builds the schedule around them, with site preparation running while the machine is built.
Lead times for equipment vary widely; replace the build row with the vendor's quoted lead time.
Who it's for: Manufacturing engineers, plant managers and equipment project leads.
How to use it
- Open the plan. Click Use this template. The tasks load as a live Gantt chart without signing in.
- Use the vendor lead time. Set the build row to the lead time on the vendor's quote.
- Run site prep in parallel. Start site preparation early enough that it finishes before shipping arrives.
- Share. Send a read-only link to the vendor and the plant team.
Planning tips
- Write acceptance criteria into the purchase order so FAT and SAT have clear pass marks.
- Confirm utilities (power, air, water) before the equipment arrives.
- Plan training before handover, not after.
Frequently asked questions
- What is the difference between FAT and SAT?
- A factory acceptance test checks the equipment at the vendor before shipping. A site acceptance test checks it after installation at your plant.
- Can I add validation steps for regulated industries?
- Yes. Add rows for installation, operational and performance qualification after the site acceptance test.
- Is it free?
- Yes. Opening and editing the template is free, and a free account saves one project. Downloading the chart as PDF or CSV needs Solo.
Related templates and guides
- Plant Maintenance Shutdown Gantt chart template
- Warehouse Relocation Plan Gantt chart template
- Manufacturing New Product Introduction Gantt chart template
- Microsoft Project alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.