Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 13 tasks across 4 phases, about 14 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Plan | Requirements and capacity | 7 days | Day 1 | Nothing (starts first) |
| Plan | Site selection and lease | 20 days | Day 8 | Requirements and capacity |
| Plan | Layout design | 10 days | Day 28 | Site selection and lease |
| Build | Racking installation | 15 days | Day 38 | Layout design |
| Build | WMS and scanner setup | 10 days | Day 53 | Racking installation |
| Build | Dock and safety checks | 5 days | Day 63 | WMS and scanner setup |
| Build | Staff training at new site | 3 days | Day 68 | Dock and safety checks |
| Move | Full inventory count | 2 days | Day 71 | Staff training at new site |
| Move | Move slow-moving stock | 5 days | Day 73 | Full inventory count |
| Move | Move fast-moving stock | 3 days | Day 78 | Move slow-moving stock |
| Move | Go-live at new site | 1 day | Day 81 | Move fast-moving stock |
| Close | Stabilize operations | 10 days | Day 82 | Go-live at new site |
| Close | Hand back old site | 5 days | Day 92 | Stabilize operations |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this warehouse relocation plan
A warehouse move has to keep orders flowing. This plan builds out the new site first (layout, racking, systems), then moves stock in phases, and only hands the old building back after the new one is shipping reliably.
Durations assume a single mid-sized warehouse. Add rows for each move wave if you transfer in several stages.
Who it's for: Operations managers, logistics leads and 3PL project managers.
How to use it
- Open the plan. Click Use this template. The tasks load as a live Gantt chart without signing in.
- Plan your waves. Split the move rows into waves by product group or zone.
- Protect peak season. Shift the move so it doesn't land on your busiest weeks.
- Share. Send a read-only link to carriers and the landlord.
Planning tips
- Move slow-moving stock first so the busy lines move last and fastest.
- Count inventory before and after the move.
- Keep the old site available until the new one has run cleanly for a while.
Frequently asked questions
- How do you move a warehouse without stopping shipping?
- Build out the new site fully, move stock in phases starting with slow movers, and switch shipping over on a planned go-live day.
- Can I add a second site?
- Yes. Copy the build and move rows for each site.
- Is it free?
- Yes. Opening and editing the template is free, and a free account saves one project. Downloading the chart as PDF or CSV needs Solo.
Related templates and guides
- Office Move Plan Gantt chart template
- Equipment Installation and Commissioning Gantt chart template
- Plant Maintenance Shutdown Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.