Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 4 phases, about 12 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Plan | Scope freeze and work list | 14 days | Day 1 | Nothing (starts first) |
| Plan | Contractor booking | 14 days | Day 15 | Scope freeze and work list |
| Plan | Order parts and materials | 30 days | Day 29 | Contractor booking |
| Plan | Safety and permit planning | 10 days | Day 59 | Order parts and materials |
| Shutdown | Controlled shutdown | 1 day | Day 69 | Safety and permit planning |
| Shutdown | Isolation and lockout | 1 day | Day 70 | Controlled shutdown |
| Shutdown | Inspections | 3 days | Day 71 | Isolation and lockout |
| Shutdown | Repairs and replacements | 5 days | Day 74 | Inspections |
| Restart | Remove isolations | 1 day | Day 79 | Repairs and replacements |
| Restart | Testing and commissioning | 2 days | Day 80 | Remove isolations |
| Restart | Startup | 1 day | Day 82 | Testing and commissioning |
| Review | Post-shutdown review | 2 days | Day 83 | Startup |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this plant maintenance shutdown
Most of a shutdown's success is decided before the plant stops: scope frozen, parts on site, contractors booked and safety plans approved. The outage itself is short and sequenced around isolation, work, testing and safe restart.
This plan fits a planned maintenance outage at a manufacturing or processing site. Your site's safety procedures always take precedence.
Who it's for: Maintenance managers, plant engineers and shutdown coordinators.
How to use it
- Open the plan. Click Use this template.
- Use real lead times. Set the parts row to your longest supplier lead time.
- Break down the outage. Add a row per work package between isolation and testing.
- Share with contractors. Send a read-only link to contractors and operations.
Planning tips
- Freeze scope early; late additions are a common cause of overruns.
- Have critical spares on site before shutdown starts.
- Hold the post-shutdown review while details are fresh.
Frequently asked questions
- What is a turnaround?
- A planned outage where a plant or unit is shut down for maintenance, inspection and upgrades.
- Can I schedule by the hour?
- No. The editor schedules whole days, so use it for the overall shutdown timeline and keep hour-by-hour outage plans in your maintenance system.
- Is it free?
- Yes. Opening and editing the template is free.
Related templates and guides
- Manufacturing New Product Introduction Gantt chart template
- Construction Schedule Gantt chart template
- Compliance Audit Preparation Plan Gantt chart template
- Equipment Installation and Commissioning Gantt chart template
- Microsoft Project alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.