Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 4 phases, about 20 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Plan | Set goal and budget | 7 days | Day 1 | Nothing (starts first) |
| Plan | Donor research and segmentation | 14 days | Day 8 | Set goal and budget |
| Plan | Case for support | 10 days | Day 22 | Donor research and segmentation |
| Quiet phase | Board and major donor asks | 30 days | Day 32 | Case for support |
| Quiet phase | Lead gift commitments | 14 days | Day 62 | Board and major donor asks |
| Public phase | Campaign page and materials | 10 days | Day 76 | Lead gift commitments |
| Public phase | Public launch | 1 day | Day 86 | Campaign page and materials |
| Public phase | Email and mail appeals | 21 days | Day 87 | Public launch |
| Public phase | Fundraising event | 1 day | Day 108 | Email and mail appeals |
| Public phase | Peer-to-peer push | 14 days | Day 109 | Fundraising event |
| Steward | Thank-you letters and receipts | 7 days | Day 123 | Peer-to-peer push |
| Steward | Impact report to donors | 14 days | Day 130 | Thank-you letters and receipts |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this nonprofit fundraising campaign
Fundraising campaigns commonly start with a quiet phase: securing lead gifts from major donors before going public, so the public launch can announce real momentum. This plan follows that structure and ends with stewardship, because thanking donors is part of the campaign.
It fits an annual appeal or a focused campaign for a program or capital need.
Who it's for: Development directors, executive directors and fundraising volunteers.
How to use it
- Open the plan. Click Use this template.
- Set the public launch. Adjust the planning and quiet-phase durations until the public launch lands on your target date.
- Assign asks. Give each major-donor ask an owner from staff or the board.
- Share with the board. Send a read-only link for board meetings.
Planning tips
- Thank donors quickly; schedule it as a task, not an afterthought.
- Have the case for support ready before the first major ask.
- Plan the impact report when you plan the campaign.
Frequently asked questions
- What is the quiet phase of a campaign?
- The period before public launch when an organization secures leadership and major gifts.
- Can I track multiple appeals?
- Yes. Add rows per appeal or channel and give each its own owner.
- Is it free?
- Yes. Opening and editing the template is free; a free account saves one project.
Related templates and guides
- Grant Proposal Timeline Gantt chart template
- Event Planning Timeline Gantt chart template
- Marketing Launch Plan Gantt chart template
- Volunteer Program Launch Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.