Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 15 tasks across 5 phases, about 43 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Setup | Concept and business plan | 21 days | Day 1 | Nothing (starts first) |
| Setup | Lease negotiation and signing | 30 days | Day 22 | Concept and business plan |
| Permits | Building permits | 30 days | Day 52 | Lease negotiation and signing |
| Permits | Liquor license application | 60 days | Day 82 | Building permits |
| Permits | Health permit | 14 days | Day 142 | Liquor license application |
| Build | Build-out and kitchen install | 60 days | Day 156 | Health permit |
| Build | Equipment delivery and setup | 7 days | Day 216 | Build-out and kitchen install |
| Build | Fire and health inspections | 7 days | Day 223 | Equipment delivery and setup |
| Operations | Menu development and costing | 21 days | Day 230 | Fire and health inspections |
| Operations | Suppliers and POS setup | 7 days | Day 251 | Menu development and costing |
| Operations | Hiring staff | 21 days | Day 258 | Suppliers and POS setup |
| Operations | Staff training | 10 days | Day 279 | Hiring staff |
| Open | Friends and family service | 3 days | Day 289 | Staff training |
| Open | Soft opening | 7 days | Day 292 | Friends and family service |
| Open | Grand opening | 1 day | Day 299 | Soft opening |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this restaurant opening plan
Restaurant openings are often paced by permits and inspections: building, fire and health, and a liquor license where you serve alcohol. This plan keeps them visible next to the build-out and hiring.
Requirements and timelines vary by city and state, so check with your local authorities and replace the placeholders.
Who it's for: Restaurant owners, chefs opening their first place, and hospitality consultants.
How to use it
- Open the plan. Click Use this template.
- Run permits in parallel. Unlink the liquor license so it starts at lease signing. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Schedule hiring backward. Make staff training finish right before the soft opening.
- Share with partners. Send a read-only link to investors and your contractor.
Planning tips
- Start the liquor license as early as your jurisdiction allows.
- Book final inspections before you announce an opening date.
- Cost the menu before you print it.
Frequently asked questions
- How long does it take to open a restaurant?
- Often several months to a year from lease to opening, depending on build-out and permits. This template spans about ten months if every task runs in sequence; overlapping permits and build-out shortens it.
- Does the template cover licensing in my state?
- No template can. It reserves rows for common permits; check your city and state requirements.
- Can I share it with my contractor?
- Yes. Read-only share links need no account.
Related templates and guides
- Kitchen Remodel Timeline Gantt chart template
- Construction Schedule Gantt chart template
- Event Planning Timeline Gantt chart template
- Medical Clinic Opening Plan Gantt chart template
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.