Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 5 phases, about 8 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Design | Site assessment and measurements | 2 days | Day 1 | Nothing (starts first) |
| Design | Landscape design | 10 days | Day 3 | Site assessment and measurements |
| Design | Material and plant selection | 5 days | Day 13 | Landscape design |
| Prepare | Utility locate and marking | 3 days | Day 18 | Material and plant selection |
| Prepare | Removal and demolition | 3 days | Day 21 | Utility locate and marking |
| Prepare | Grading and drainage | 4 days | Day 24 | Removal and demolition |
| Build | Patio, paths and walls | 10 days | Day 28 | Grading and drainage |
| Build | Irrigation installation | 3 days | Day 38 | Patio, paths and walls |
| Build | Lighting rough-in | 2 days | Day 41 | Irrigation installation |
| Plant | Soil preparation | 2 days | Day 43 | Lighting rough-in |
| Plant | Trees and shrubs | 3 days | Day 45 | Soil preparation |
| Plant | Beds and mulch | 3 days | Day 48 | Trees and shrubs |
| Plant | Lawn seed or sod | 2 days | Day 51 | Beds and mulch |
| Close | Final walkthrough and care instructions | 1 day | Day 53 | Lawn seed or sod |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this landscaping project
Landscaping has a natural order: mark buried utilities, fix grading and drainage, build hardscape such as patios and walls, run irrigation, and only then plant. Planting first means digging up new plants later.
It fits a residential or small commercial yard project. Weather and planting seasons will shift the dates.
Who it's for: Homeowners, landscape designers and landscaping contractors.
How to use it
- Open the plan. Click Use this template.
- Respect the season. Adjust durations so planting falls in a suitable season for your region.
- Add weather float. Lengthen grading and hardscape rows to allow for rain days.
- Share with the crew. Send a read-only link to the contractor and homeowner.
Planning tips
- Use your area's utility-locate service before digging.
- Fix drainage before building patios against the house.
- Plan watering for new plants right after planting.
Frequently asked questions
- What order should landscaping be done in?
- Typically utilities marked, removal, grading and drainage, hardscape, irrigation and lighting, then soil and planting.
- Can I plan a multi-season project?
- Yes. Plans can run up to two years.
- Is it free?
- Yes. Opening and editing the template is free.
Related templates and guides
- Home Renovation Plan Gantt chart template
- Construction Schedule Gantt chart template
- Bathroom Remodel Gantt chart template
- Construction scheduling with a Gantt chart
- Microsoft Project alternative for schedules
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.