Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 10 tasks across 4 phases, about 16 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Discover | Customer interviews and problem framing | 14 days | Day 1 | Nothing (starts first) |
| Discover | Solution sketches and prioritization | 7 days | Day 15 | Customer interviews and problem framing |
| Release one | Core workflow improvements | 21 days | Day 22 | Solution sketches and prioritization |
| Release one | Release one QA and rollout | 5 days | Day 43 | Core workflow improvements |
| Release two | Integrations and reporting | 28 days | Day 48 | Release one QA and rollout |
| Release two | Private beta with design partners | 14 days | Day 76 | Integrations and reporting |
| Release two | Beta feedback fixes | 7 days | Day 90 | Private beta with design partners |
| Launch | General availability launch | 2 days | Day 97 | Beta feedback fixes |
| Launch | Adoption review | 10 days | Day 99 | General availability launch |
| Launch | Next-quarter planning checkpoint | 3 days | Day 109 | Adoption review |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this product roadmap
A roadmap on a timeline answers the question every stakeholder asks: roughly when? This template lays out discovery, two releases, a beta and a launch, with a planning checkpoint at the end so the roadmap is revisited rather than treated as a promise.
Keep bars at the level of themes or epics. Detailed tasks belong in sprint plans; the roadmap should stay readable on one screen.
Who it's for: Product managers, founders and heads of product presenting plans to leadership, sales or customers.
How to use it
- Open the roadmap. Click Use this template. The roadmap loads as a live Gantt chart.
- Rename the themes. Replace the example releases with your own themes or epics; keep each bar to a few weeks.
- Show confidence. Mark later items At risk or add a note that dates are estimates, so the roadmap isn't read as a commitment.
- Share a read-only link. Send the link to sales and leadership instead of a static slide that goes stale.
Planning tips
- Use fewer, larger bars; a roadmap with fifty rows is a backlog.
- Put the planning checkpoint on the chart so the roadmap gets revisited.
- Keep customer-facing and internal versions separate if dates are sensitive.
Frequently asked questions
- What is the difference between a roadmap and a project plan?
- A roadmap shows themes and rough timing over months; a project plan breaks one piece of work into tasks with owners and dependencies.
- Should a roadmap have exact dates?
- Many teams use months or quarters for later items and firmer dates only for the next release. Mark estimates clearly.
- Can I share it without giving edit access?
- Yes. Read-only share links are free and recipients don't need an account.
Related templates and guides
- Project Roadmap Gantt chart template
- Software Sprint Plan Gantt chart template
- Marketing Launch Plan Gantt chart template
- Mobile App Development Plan Gantt chart template
- Product launch roadmap
- Marketing campaign timeline maker
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template