Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 21 tasks across 4 phases, about 12 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Owner | Duration | Starts | Depends on |
|---|---|---|---|---|---|
| Prepare | Needs assessment and requirements | Project lead | 10 days | Day 1 | Nothing (starts first) |
| Prepare | Market research and vendor list | Procurement officer | 5 days | Day 1 | Nothing (starts first) |
| Prepare | Budget approval | Finance | 5 days | Day 11 | Needs assessment and requirements |
| Prepare | Draft RFP document | Procurement officer | 8 days | Day 11 | Needs assessment and requirements, Market research and vendor list |
| Prepare | Evaluation criteria and scoring sheet | Project lead | 3 days | Day 11 | Needs assessment and requirements |
| Prepare | Legal and procurement review | Legal | 5 days | Day 19 | Draft RFP document, Evaluation criteria and scoring sheet |
| Solicit | RFP issued | Milestone | Day 24 | Legal and procurement review, Budget approval | |
| Solicit | Pre-proposal conference | Project lead | 1 day | Day 24 | RFP issued |
| Solicit | Vendor questions period | Procurement officer | 10 days | Day 24 | RFP issued |
| Solicit | Answers and addenda published | Procurement officer | 3 days | Day 34 | Vendor questions period, Pre-proposal conference |
| Solicit | Vendor response period | 25 days | Day 24 | RFP issued | |
| Solicit | Proposals due | Milestone | Day 49 | Vendor response period, Answers and addenda published | |
| Evaluate | Compliance check | Procurement officer | 2 days | Day 49 | Proposals due |
| Evaluate | Evaluation committee scoring | Evaluation committee | 10 days | Day 51 | Compliance check |
| Evaluate | Shortlist demos and interviews | Evaluation committee | 5 days | Day 61 | Evaluation committee scoring |
| Evaluate | Reference checks | Project lead | 3 days | Day 61 | Evaluation committee scoring |
| Evaluate | Best and final offers | Procurement officer | 5 days | Day 66 | Shortlist demos and interviews |
| Award | Award recommendation and approval | Evaluation committee | 2 days | Day 71 | Best and final offers, Reference checks |
| Award | Notice of intent to award | Milestone | Day 73 | Award recommendation and approval | |
| Award | Protest period | 5 days | Day 73 | Notice of intent to award | |
| Award | Contract negotiation and signature | Legal | 10 days | Day 78 | Protest period |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 87 days instead of the 117 it would take one task at a time. The 14 darker bars are the critical path: a day lost on any of them moves the finish date.
About this rfp timeline
An RFP is one of the few projects where half the schedule is outside your control. Once it is issued, vendors have a fixed window to ask questions and respond, and the dates in the RFP document become commitments you have published. A realistic timeline before issue is what keeps the evaluation from being rushed at the end.
This template is the buyer's side of a request for proposal, about twelve weeks from the needs assessment to a signed contract. It covers preparation (requirements, market research, budget, evaluation criteria and review), the solicitation (issue, pre-proposal conference, questions, addenda and the response period), the evaluation (compliance check, scoring, demos, references and best and final offers) and the award. The RFP issue date, proposals due and notice of intent to award are milestones.
Every jurisdiction and organisation has its own rules for minimum response periods, protest periods and approvals. Treat the durations here as examples and replace them with what your procurement rules require.
Who it's for: Procurement officers, IT and operations leads and public-sector project managers running a competitive selection for a service or system.
How to use it
- Use this template. Click Use this template. The plan opens in the editor with prepare, solicit, evaluate and award as lanes, owners on the buyer's tasks and the key dates as milestones. No sign-up is needed.
- Apply your procurement rules. Change the response period, questions period and protest period to what your policy or the law requires. These are the durations you cannot shorten later, so set them first.
- Publish the dates from the chart. Copy the RFP issued, questions deadline, proposals due and award dates from the chart into the RFP document's schedule section, so the published dates and the plan are the same.
- Share it with the evaluation committee. Share a read-only link so committee members can block the scoring and demo weeks in their calendars before proposals arrive. Members do not need an account.
The dates you publish and the dates you keep
The RFP document usually lists a schedule: issue date, deadline for questions, date answers will be posted, proposals due, and an anticipated award date. The first four are commitments to vendors and are hard to move without an addendum. The award date is an estimate, but it is the one stakeholders remember.
This template keeps the published dates as milestones and tasks driven by the preparation work, so you set them from a plan rather than a calendar. The critical path runs through the requirements, the draft RFP and its review, the vendor response period, then the compliance check, scoring, demos, best and final offers, the award recommendation, the protest period and the contract. Budget approval has eight days of slack and the evaluation criteria five; reference checks have a week in hand, because they run alongside the demos and best and final offers.
Planning the evaluation before proposals arrive
Evaluation is where RFP timelines slip, usually because the committee was not booked in advance or the scoring criteria were still being argued about after proposals were opened. Writing the criteria and the scoring sheet before the RFP is issued, as this plan does, avoids both: vendors can be told how they will be scored, and the committee knows exactly what they will be asked to do.
Book the committee's time for the scoring and demo weeks as soon as the RFP is issued. Ten working days of scoring here assumes members can give it real time; if they cannot, lengthen the task now rather than finding out when proposals are due.
Planning tips
- Write the evaluation criteria before you issue the RFP, and publish the weighting if your rules allow it.
- Run the questions period inside the response window and post all answers to all vendors at once, as an addendum.
- Leave time between proposals due and scoring for the compliance check. A proposal that is missing a required form is easier to handle before scoring starts.
- Check reference calls and demos against the same criteria as the written proposals, so the final score is consistent.
- Keep contract negotiation on the plan. It often takes as long as the evaluation, and the service start date depends on it.
Frequently asked questions
- How long does an RFP process take?
- It depends on the size of the purchase and the rules you follow. This example runs about twelve weeks from the needs assessment to a signed contract, with a 25-day response period. Public bodies often have minimum periods set by policy or law, so check yours.
- What are the stages of an RFP timeline?
- Preparation (requirements, budget, evaluation criteria and review), solicitation (issue, questions and answers, response period), evaluation (compliance check, scoring, demos, references, best and final offers) and award (recommendation, notice of intent, any protest period and the contract).
- What dates go in the RFP document?
- Usually the issue date, the deadline for vendor questions, when answers will be posted, the proposal due date and time, any pre-proposal conference and an anticipated award date. Taking them from this chart keeps the document and the plan in step.
- Can I use this RFP timeline in Excel?
- Yes. Download CSV gives you every task with its owner, start date, end date, phase and dependencies, which opens in Excel or Google Sheets.
- Is this RFP timeline template free?
- Yes. Opening and editing it in the browser is free with no sign-up, and the CSV download on this page is free. A free account keeps one saved project.
Related templates and guides
- SaaS Customer Implementation Gantt chart template
- ERP Implementation Plan Gantt chart template
- CRM Implementation Plan Gantt chart template
- Project Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.