Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 22 tasks across 5 phases, about 15 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Define | Project charter | 4 days | Day 1 | Nothing (starts first) |
| Define | Voice of the customer and CTQs | 6 days | Day 5 | Project charter |
| Define | High-level process map (SIPOC) | 3 days | Day 5 | Project charter |
| Define | Define tollgate | 1 day | Day 11 | Voice of the customer and CTQs, High-level process map (SIPOC) |
| Measure | Data collection plan | 4 days | Day 12 | Define tollgate |
| Measure | Measurement system analysis | 6 days | Day 16 | Data collection plan |
| Measure | Baseline data collection | 15 days | Day 22 | Measurement system analysis |
| Measure | Baseline capability | 3 days | Day 37 | Baseline data collection |
| Measure | Measure tollgate | 1 day | Day 40 | Baseline capability |
| Analyze | Detailed process map | 5 days | Day 12 | Define tollgate |
| Analyze | Root cause analysis | 8 days | Day 41 | Measure tollgate, Detailed process map |
| Analyze | Hypothesis testing | 6 days | Day 49 | Root cause analysis |
| Analyze | Analyze tollgate | 1 day | Day 55 | Hypothesis testing |
| Improve | Solution design and selection | 6 days | Day 56 | Analyze tollgate |
| Improve | Pilot | 15 days | Day 62 | Solution design and selection |
| Improve | Pilot results review | 3 days | Day 77 | Pilot |
| Improve | Full implementation | 10 days | Day 80 | Pilot results review |
| Improve | Improve tollgate | 1 day | Day 90 | Full implementation |
| Control | Control plan and SOP updates | 5 days | Day 80 | Pilot results review |
| Control | Control charts and monitoring | 10 days | Day 90 | Full implementation |
| Control | Handover to process owner | 2 days | Day 100 | Control charts and monitoring, Control plan and SOP updates |
| Control | Control tollgate and closure | 1 day | Day 102 | Handover to process owner, Improve tollgate |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 102 days instead of the 116 it would take one task at a time. The 18 darker bars are the critical path: a day lost on any of them moves the finish date.
About this six sigma dmaic project
DMAIC projects are built around tollgates. Each phase (Define, Measure, Analyze, Improve, Control) ends with a review where the sponsor confirms the phase is complete before the team moves on. This template puts those tollgates on the chart as tasks, so the plan shows both the work and the decision points.
It suits a Green Belt or Black Belt project improving one process over about four to five months. The Measure phase includes validating the measurement system before collecting baseline data, and the Improve phase includes a pilot before full implementation, which are the two steps teams most often rush.
Rename the tasks to match your organisation's DMAIC checklist; the dependencies between phases stay the same.
Who it's for: Six Sigma Green Belts and Black Belts, continuous improvement leads and project sponsors.
How to use it
- Use this template. Click Use this template. The five DMAIC phases open as lanes, and each tollgate is a one-day task that the next phase waits for.
- Book the tollgates. Agree tollgate dates with your sponsor and move the tollgate tasks to them. The work before each tollgate shows whether the date is realistic.
- Size data collection. Baseline data collection and the pilot are usually the longest tasks. Set them to cover enough of your process cycle to see normal variation.
- Report to the sponsor. Share a read-only link before each tollgate so the sponsor sees progress and the next phase's plan.
Tollgates and overlap
Strict DMAIC finishes each phase before the next begins, and the tollgates in this template enforce that for the main work. Two tasks deliberately overlap: the detailed process map starts after the Define tollgate, during Measure, because mapping the process helps decide what to measure. The control plan is drafted after the pilot results review, during full implementation, so it is ready when the improvement goes live.
Measurement system analysis comes before baseline data collection. If the measurement system cannot be trusted, the baseline, the root cause analysis and the proof of improvement all fall with it.
Closing the project properly
The Control phase hands the improved process back to its owner with a control plan, updated procedures and monitoring in place. The project only closes once the control charts show the gain is holding, which is why monitoring runs for two weeks before the final tollgate.
Planning tips
- Keep the charter's problem statement free of solutions; it makes the Analyze phase honest.
- Collect baseline data over a full business cycle if you can.
- Pilot on a small part of the process before full implementation, and plan time to act on what the pilot shows.
- Agree who owns the control plan before handover, not at the closing tollgate.
Frequently asked questions
- What are the DMAIC phases?
- Define, Measure, Analyze, Improve and Control. Each phase has its own deliverables and usually ends with a tollgate review with the project sponsor.
- How long does a DMAIC project take?
- Many Green Belt projects take three to six months. This template is about five months with the example durations; your data collection and pilot periods will drive the real length.
- Can I show tollgates as milestones?
- Yes. The tollgates are one-day tasks in the template. In the editor you can change their type to milestone so they show as diamonds.
- Is this suitable for Lean projects?
- The structure works for any phased improvement project. For a Lean kaizen event, shorten the Measure and Analyze phases to days rather than weeks.
Related templates and guides
- Compliance Audit Preparation Plan Gantt chart template
- Strategic Planning Process Gantt chart template
- Manufacturing Production Plan Gantt chart template
- ISO 27001 Certification Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.