Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 4 phases, about 24 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Gather | Stakeholder surveys and interviews | 14 days | Day 1 | Nothing (starts first) |
| Gather | Environmental and competitor scan | 10 days | Day 15 | Stakeholder surveys and interviews |
| Gather | Performance review of current plan | 5 days | Day 25 | Environmental and competitor scan |
| Decide | Leadership retreat | 2 days | Day 30 | Performance review of current plan |
| Decide | Priorities and goals | 7 days | Day 32 | Leadership retreat |
| Decide | Draft strategic plan | 10 days | Day 39 | Priorities and goals |
| Decide | Staff and stakeholder feedback | 7 days | Day 49 | Draft strategic plan |
| Approve | Board review and approval | 7 days | Day 56 | Staff and stakeholder feedback |
| Approve | Translate goals into team plans | 10 days | Day 63 | Board review and approval |
| Review | Communicate the plan | 3 days | Day 73 | Translate goals into team plans |
| Review | First quarter of execution | 90 days | Day 76 | Communicate the plan |
| Review | First quarterly review | 1 day | Day 166 | First quarter of execution |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this strategic planning process
Strategic plans fail quietly when they are approved and filed. This timeline covers the process of making the plan — input, analysis, a leadership retreat, drafting and approval — and puts the first quarterly review on the chart.
It fits companies and nonprofits building a multi-year plan.
Who it's for: Executive directors, CEOs, strategy leads and board chairs.
How to use it
- Open the plan. Click Use this template.
- Fit your board calendar. Adjust durations so board review lands on a scheduled board meeting.
- Assign owners. Give each row an owner on the leadership team.
- Share with the board. Send a read-only link for board updates.
Planning tips
- Gather input before the retreat so the discussion starts from evidence.
- Limit priorities to a few the organization can fund.
- Schedule the first review before the plan is published.
Frequently asked questions
- How long does strategic planning take?
- The planning steps in this template take about two and a half months in sequence; the chart then runs through the first quarter of execution to the first quarterly review.
- Can I track the plan's goals here?
- Yes. After approval, open a new plan with each goal's initiatives as tasks.
- Is it free?
- Yes. Opening and editing the template is free.
Related templates and guides
- Project Roadmap Gantt chart template
- Action Plan Gantt chart template
- Annual Budget Planning Gantt chart template
- Product Roadmap Gantt chart template
- Merger Integration Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.