Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 11 tasks across 4 phases, about 7 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Plan | Goals, audience and key message | 3 days | Day 1 | Nothing (starts first) |
| Plan | Channel plan | 2 days | Day 4 | Goals, audience and key message |
| Plan | Creative brief | 2 days | Day 6 | Channel plan |
| Produce | Copywriting | 5 days | Day 8 | Creative brief |
| Produce | Design and video | 10 days | Day 13 | Copywriting |
| Produce | Internal approvals | 3 days | Day 23 | Design and video |
| Launch | Schedule posts | 2 days | Day 26 | Internal approvals |
| Launch | Launch day | 1 day | Day 28 | Schedule posts |
| Launch | Campaign run and community management | 20 days | Day 29 | Launch day |
| Review | Mid-campaign check | 1 day | Day 49 | Campaign run and community management |
| Review | Results review | 2 days | Day 50 | Mid-campaign check |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this social media campaign plan
A social campaign needs its content ready before it goes live. This plan sets goals and the channel mix, produces and approves the content, schedules it, runs the campaign with community management, and finishes with a results review.
Change the run length to match your campaign; everything after it moves along.
Who it's for: Social media managers, marketing teams and agency account leads.
How to use it
- Open the plan. Click Use this template. The tasks load as a live Gantt chart without signing in.
- Set the run length. Change the campaign run row to the number of days the campaign lasts.
- Add approval time. Lengthen approvals if legal or a client needs to sign off.
- Share. Send a read-only link to the client or stakeholders.
Planning tips
- Decide how you will measure success before producing content.
- Leave time for approvals; it is the step that slips most often.
- Plan who replies to comments during the campaign.
Frequently asked questions
- How far ahead should a social campaign be planned?
- This example starts about four weeks before launch, mostly for content production and approvals.
- Can I plan an ongoing content calendar?
- Yes. The content marketing calendar template is built for recurring publishing.
- Is it free?
- Yes. Opening and editing the template is free, and a free account saves one project. Downloading the chart as PDF or CSV needs Solo.
Related templates and guides
- Content Marketing Plan Gantt chart template
- Marketing Launch Plan Gantt chart template
- Rebrand Project Plan Gantt chart template
- Marketing campaign timeline maker
- Product launch roadmap
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.