Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 12 tasks across 4 phases, about 10 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Design | Site survey and roof check | 2 days | Day 1 | Nothing (starts first) |
| Design | System design and quote | 5 days | Day 3 | Site survey and roof check |
| Design | Contract signed | 1 day | Day 8 | System design and quote |
| Approvals | Building and electrical permits | 15 days | Day 9 | Contract signed |
| Approvals | Utility interconnection application | 20 days | Day 24 | Building and electrical permits |
| Install | Equipment delivery | 5 days | Day 44 | Utility interconnection application |
| Install | Roof mounting and racking | 1 day | Day 49 | Equipment delivery |
| Install | Panel installation | 1 day | Day 50 | Roof mounting and racking |
| Install | Inverter and electrical work | 2 days | Day 51 | Panel installation |
| Commission | Local inspection | 5 days | Day 53 | Inverter and electrical work |
| Commission | Utility permission to operate | 10 days | Day 58 | Local inspection |
| Commission | System switch-on and monitoring setup | 1 day | Day 68 | Utility permission to operate |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this solar panel installation project
The physical install of a rooftop solar system is often quick. Permits, inspection and the utility's interconnection approval usually take longer, so this plan starts them early and shows them clearly.
Requirements vary by location and utility. Use the permit and interconnection rows as reminders to check what applies.
Who it's for: Homeowners, solar installers and small commercial building owners.
How to use it
- Open the plan. Click Use this template. The tasks load as a live Gantt chart without signing in.
- Ask your installer. Replace approval durations with the times your installer sees locally.
- Add battery storage. Add rows for a battery install if your system includes one.
- Share. Send a read-only link to your installer or household.
Planning tips
- Check roof condition first; replacing a roof after panels go on costs more.
- Don't switch the system on before the utility gives permission to operate.
- Keep permit and inspection records for warranty and resale.
Frequently asked questions
- How long does a solar installation take?
- The install itself is often a few days; approvals usually set the overall timeline. This example runs about two to three months.
- Is this electrical or legal advice?
- No. It is a planning template; follow your installer, utility and local authority.
- Is it free?
- Yes. Opening and editing the template is free, and a free account saves one project. Downloading the chart as PDF or CSV needs Solo.
Related templates and guides
- Home Renovation Plan Gantt chart template
- Landscaping Project Gantt chart template
- Construction Schedule Gantt chart template
- Construction scheduling with a Gantt chart
- Microsoft Project alternative for schedules
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.