Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 15 tasks across 4 phases, 15 days from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Owner | Duration | Starts | Depends on |
|---|---|---|---|---|---|
| Make-ready | Confirm truss delivery date | Project engineer | 1 day | Day 1 | Nothing (starts first) |
| Make-ready | Answer open RFIs on level 2 layout | Project engineer | 2 days | Day 2 | Confirm truss delivery date |
| Make-ready | Weekly trade coordination meeting | Superintendent | 1 day | Day 1 | Nothing (starts first) |
| Level 1 | Level 1 electrical rough-in | Electrical contractor | 5 days | Day 2 | Weekly trade coordination meeting |
| Level 1 | Level 1 plumbing rough-in | Plumbing contractor | 4 days | Day 2 | Weekly trade coordination meeting |
| Level 1 | Level 1 HVAC ductwork | HVAC contractor | 5 days | Day 2 | Weekly trade coordination meeting |
| Level 1 | Level 1 rough-in inspection | Superintendent | 1 day | Day 7 | Level 1 electrical rough-in, Level 1 plumbing rough-in, Level 1 HVAC ductwork |
| Level 1 | Level 1 insulation | Insulation contractor | 3 days | Day 8 | Level 1 rough-in inspection |
| Level 2 | Level 2 wall framing | Framing contractor | 4 days | Day 4 | Answer open RFIs on level 2 layout, Weekly trade coordination meeting |
| Level 2 | Level 2 sheathing and blocking | Framing contractor | 2 days | Day 8 | Level 2 wall framing |
| Level 2 | Level 2 electrical rough-in | Electrical contractor | 5 days | Day 10 | Level 2 sheathing and blocking, Level 1 electrical rough-in |
| Level 2 | Level 2 plumbing rough-in | Plumbing contractor | 4 days | Day 10 | Level 2 sheathing and blocking, Level 1 plumbing rough-in |
| Roof | Set roof trusses | Framing contractor | 3 days | Day 10 | Level 2 sheathing and blocking, Confirm truss delivery date |
| Roof | Roof sheathing | Framing contractor | 2 days | Day 13 | Set roof trusses |
| Roof | Level 2 rough-in and roof dry-in inspection | Superintendent | 1 day | Day 15 | Level 2 electrical rough-in, Level 2 plumbing rough-in, Roof sheathing |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 15 days instead of the 43 it would take one task at a time. The 8 darker bars are the critical path: a day lost on any of them moves the finish date.
About this 3-week look-ahead schedule
The master schedule says when the building will be finished. The look-ahead says what each trade is doing on site over the next three weeks and what has to be in place before they can start. Superintendents update it every week and walk it through with the foremen at the coordination meeting.
This template is a three-week window on a two-storey wood-frame building, at the point where level 1 is in rough-in, level 2 is being framed and the roof is next. It has three kinds of task: make-ready work that removes constraints (confirming a delivery, answering RFIs), trade work by area, and inspections that hold the next trade until they pass. Every task has a trade as its owner, and no trade is in two places at once.
Durations are in working days and are examples. Replace the trades, areas and durations with your own, and roll the window forward a week each time you update it.
Who it's for: Superintendents, assistant superintendents and project engineers who run the weekly trade coordination meeting.
How to use it
- Use this template. Click Use this template. The look-ahead opens in the editor with each area as a lane, every trade as an owner and the inspection gates linked. No sign-up is needed.
- Load your next three weeks. Replace the areas and tasks with the work your master schedule shows for the next 15 working days. Keep the trade as the owner on every bar so overlaps show up.
- Add the constraints. For each task, ask what would stop the crew starting on the day: a delivery, an RFI, a permit, an inspection, a predecessor trade. Add the ones that are not cleared yet as make-ready tasks and link them in front.
- Walk it at the meeting, then roll it. Share a read-only link before the coordination meeting so foremen can check their dates on their phones. After the meeting, mark progress, drop the finished week and add the next one.
Look-ahead versus master schedule
The master schedule is the contract-level plan: phases, long-lead items and the completion date, usually maintained by the scheduler or project manager. The look-ahead takes the next few weeks of it and breaks them down to the level a foreman works at: which crew, which area, which day. It is updated weekly and owned by the field.
The two should agree on the big dates. If the look-ahead shows level 2 rough-in finishing a week after the master schedule does, that is a slip, and it should be raised at the meeting rather than discovered at the next monthly update. Some teams use a longer six-week window for planning materials and a three-week window for committing crews; this template is the three-week version.
Make-ready work: clearing constraints before the crew arrives
Most lost days on site are not about how fast a crew works but about the crew arriving to find something missing: trusses not delivered, a layout question unanswered, an inspection not passed. A look-ahead is the tool for finding those gaps while there is still time to close them. That is the idea behind make-ready planning in lean construction methods such as the Last Planner System.
In this template, level 2 framing waits for the RFI answers, and setting trusses waits for the delivery to be confirmed. The project engineer clears both in the first three days, so the framers are never stopped. If the RFI answers take a week instead of two days, the chart shows framing, trusses, roof sheathing and the final inspection all moving, which is the conversation to have with the design team now.
Reading this look-ahead
The critical path runs through the truss delivery check and the RFI answers, level 2 framing and sheathing, then two parallel chains (level 2 electrical rough-in, and trusses with roof sheathing) into the combined inspection on day 15. Both chains finish on the same day, so either one slipping moves the inspection.
Level 1 is not on the critical path. Its rough-in inspection and insulation are done by day 10, with five days of slack, and level 2 plumbing has a day in hand. Those are the places to absorb a lost day without moving the inspection.
Planning tips
- Keep the trade on every bar as its owner. Two bars for the same crew at the same time is the clash a look-ahead exists to catch.
- Put inspections on the chart as their own tasks. They are the gates that hold the next trade, and they need booking.
- List every open constraint as a make-ready task with an owner and a date, not as a note. A constraint without a date is the one still open on the day.
- Plan in working days and mark site holidays. A three-week look-ahead is 15 working days, not 21 calendar days.
- Roll the window every week, at the same meeting. A look-ahead that is two weeks old is a history, not a plan.
Frequently asked questions
- What is a 3-week look-ahead schedule?
- It is a short-term construction schedule covering the next three weeks of field work in detail: which trade is working where, on which days, and what has to be cleared first. It is updated weekly and used at the trade coordination meeting.
- What should a look-ahead schedule include?
- The trade work for each area, the inspections that gate the next step, deliveries, and the open constraints such as RFIs, submittals and permits, each with an owner and a date. This template has all four kinds of task.
- Who prepares the look-ahead schedule?
- Usually the superintendent, with the project engineer and the trade foremen. The foremen confirm their own crews and durations; the superintendent checks that the sequence works and nobody is in two places at once.
- Can I use this look-ahead template in Excel?
- Yes. Download CSV gives you every task with its trade, start date, end date, area and dependencies, which opens in Excel or Google Sheets.
- Is this look-ahead schedule template free?
- Yes. Opening and editing it in the browser is free with no sign-up, and the CSV download on this page is free. A free account keeps one saved project.
Related templates and guides
- Construction Schedule Gantt chart template
- Commercial Office Fit-Out Gantt chart template
- Home Renovation Plan Gantt chart template
- Milestone Chart Gantt chart template
- Construction scheduling with a Gantt chart
- Microsoft Project alternative for schedules
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.